Marketplace Development Roadmap - Coggle Diagram
Marketplace Development Roadmap
Start Date: 09 Oct 2026 (Friday)
First Working Day: 11 Oct 2026 (Sunday)
End Date: 12 Jan 2027 (Tuesday)
Duration: 68 working days — Sunday to Thursday (Friday & Saturday excluded)
Status Reference: 28 Oct 2026 — all Not Started tasks scheduled from 29 Oct
Completed Modules — 11 Oct to 28 Oct 2026
🟢 Products — DONE (original estimate: 1 week)
🟢 Add Product
🟢 Product Management
🟢 Product Import (view only)
🟢 Discounts — DONE (original estimate: 1.5 weeks)
🟢 Cart Discounts
🟢 Discount Codes
🟢 Product Discounts
🟢 Microservice Integration
🟢 Chat — DONE (original estimate: 2 weeks)
🟢 Microservice Communication
🟢 User-to-User Chat
🟢 Order-Related Chat
🟢 Notifications — DONE (original estimate: 2 weeks)
🟢 Notification System
Dashboard & User Profile Management — 29 Oct 2026 to 11 Nov 2026
Planned duration: 10 working days
🔴 Dashboard — 5 working days | 29 Oct 2026 to 04 Nov 2026
🔴 Buyer Dashboard
🔴 Seller Role
🔴 User Profile Management — 5 working days | 05 Nov 2026 to 11 Nov 2026
🔴 Edit Profile
🔴 Delete Account
🔴 Change Password
🔴 Permissions
🔴 My Accounting
Shipping & Billing — 12 Nov 2026 to 26 Nov 2026
Planned duration: 11 working days
🔴 Shipping Modes — 10 working days | 12 Nov 2026 to 25 Nov 2026
🔴 Shipping Conditions Management
🔴 Activate / Deactivate Shipping Modes
🔴 Billing Management — 1 working days | 26 Nov 2026 to 26 Nov 2026
🔴 Billing Management
Payment & Activity History — 29 Nov 2026 to 15 Dec 2026 (AM)
Planned duration: 12.5 working days
🔴 Payment — 10 working days | 29 Nov 2026 to 10 Dec 2026
🔴 Full Payment Module Development
🔴 History — 2.5 working days | 13 Dec 2026 to 15 Dec 2026 (AM)
🔴 Activity History
API & Reporting — 15 Dec 2026 (PM) to 17 Dec 2026 (AM)
Planned duration: 2 working days
🔴 API — 1 working days | 15 Dec 2026 (PM) to 16 Dec 2026 (AM)
🔴 API Development / Integration
🔴 Reports — 1 working days | 16 Dec 2026 (PM) to 17 Dec 2026 (AM)
🔴 Reporting
Unallocated Schedule Reserve — 17 Dec 2026 (PM) to 12 Jan 2027
Remaining timeline: 18.5 working days (not an original task)
Reserved for schedule flexibility; no additional features assumed
Status: ⚪ Unassigned