Solar Permitting, Qualifications to Apply to PBR, PBR Participation…
Solar Permitting
Permit By Rule (PBR) Path
1MW< X >= 5 MW
>=
150MW on disturbed lands, >2 acres of undisturbed land
DEQ Brownfields Designation
2 acres < X >= 10 acres
Qualifies for PBR
Certification by locality of compliance with applicable land use ordinances.
Submission to DEQ
IF significant impact is determined, submission of a mitigation plan
Determination: no significant impact, no mitigation plan needed
30-day public review and comment period
Interconnection agreement
Certification of
maximum generation capacity
Potential environmental impacts study: air quality standards
As relevant, analysis of impacts on natural resources.
Certification on accordance with regulations applicable to the PBR
Operating plan to meet PBR regulations
Detailed site plan with project location maps
Certification the applicant has applied for or obtained all necessary environmental permits
Applicant to hold a public meeting
localities may require the issuance of a Special or Conditional
Use Permitting
NOI and Certification
Determination
None of the above
NOI and Certification required
PV only, if building or structure where integrated materials are used is less than 50 years old.
On buildings less than 50 years old
On Single-family or duplex private residence.
Over existing parking lots or roads, impacts >= 2 acres of undisturbed areas
NOI and Certification not required
None of the above
May not qualify for PBR
Qualifications to Apply to PBR
PBR Participation Requirements
Post Submission