ACTIAN PLAN SUSUT TEGANGAN MENENGAH - Coggle Diagram
ACTIAN PLAN SUSUT TEGANGAN MENENGAH
IDENTIFIKASI DAN AUDIT DATA ( MINGGU 1 DAN 2)
A. AUDIT KWH METER DI GARDU INDUK DAN DISTRIBUSI
MEMASTIKAN ENERGI MASUK DIBANDINGKAN ENERGI KELUAR
B. SIMULASI ALIRAN DAYA (LOAD FLOW)
MENGGUNAKAN SOFTWARE ETAB DIGSILENT UNTUK PENYULANG DENGAN DROP TEGANGAN TERTINGGI
C. PEMETAAN TITIK HOTSPOT
MELAKUKAN TERMOVISION PADA SELURUH KONEKTOR DI JALUR UTAMA
PENANGANAN CEPAT QUICK WINS ( BULAN 1 - 2)
A. EKSEKUSI PEMANGKASAN POHON ( ROW)
PEMBERSIHAN JALUR DARI DAHAN POHON SECARA MENYELURUH UNTUK MENGHENTIKAN ARUS BOCOR KE TANAH
B. PERBAIKAN SAMBUNGAN BAUD DAN KLEM
MELAKUKAN PEMBERSIHAN, PENGENCANGAN ATAU MENGGANTI KONEKTOR YANG TERDETEKSI PANAS HASIL INSPEKSI TERMOVISION
C. PENYEIMBANGAN BEBAN ANTAR FASA
MENGATUR ULANG PEMBEBANAN TRAFO DISTRIBUSI AGAR BEBAN DI PENYULANG MENJADI SEIMBANG
PERBAIKAN KUALITAS DAN OPTIMASI ( BULAN 3 - 5 )
A. PEMASANGAN DAN SETTING KAPASITOR BANK
MEMASANG KAPASITOR DI TENGAH ATAU UJUNG PENYULANG YANG MEMILIKI COSPI < 0.9
B. REKONFIGURASI JARINGAN
MENGUBAH OPEN POINT UNTUK MEMBAGI BEBAN KE PENYULANG DENGAN BEBAN LEBIH RENDAH UNTUK MEMPERPENDEK JARAK TEMPUH ARUS
C. PEMBERSIHAN ISOLATOR
UNTUK AREA POLUSI TINGGI UNTUK MEMINIMALKAN ARUS RAYAP ( CREEPAGE CURRENT )
INVESTASI INFRASTRUKTUR / LONG TERM ( BULAN 6 KETAS)
A. UPRATING KONDUKTOR
PENGGANTIAN KAWAT PENGHANTAR YANG SUDAH OVERLOAD ( KHA > 80%) DENGAN PENAMPANG YANG LEBIH BESAR
B. PECAH BEBAN DAN PEMBANGUNAN JARINGAN BARU
MEMBANGUN PENYULANG BARU ATAU MENAMBAH GH UNTUK PENYULANG YANG SUDAH OVERLOAD
C. MODERENISASI ASSET
MENGGANTI ISOLATOR KERAMIK DENGAN ISOLATOR POLYMER YANG MEMILIKI SIFAT DYDROFOBIK LEBIH BARIK TERHADAP ARUS BOCOR