Quang Ninh GtP Project- 2 x 6MW-6.6KV
4 x CG260-12 (3000ekw,6.6KV)
Engine
gas piping, gas train
Gas filters
Gas pressure regulators
Gas pressure guage
Gas over pressure switch
Gas low pressure switch
Gas isolating valves
Gas leakage detectors
Gas emergency automatic shut off valves
Pressure boosting equipment
Engine lubrication system
Integral closed-circuit radiator
Exhaust system including silencer and flashings
Electric starting system (24V DC) + batteries + battery charger
Lubricating oil and grease for initial filling and consumable for site tests
Weatherproof acoustic enclosure
A 230V AC single phase load centre with circuit breakers for
Jacket water heater
Battery chargers
LED lights mounted within the acoustic enclosure with on/off switch
20A of spare capacity for future use
Anti-Vibration mounting pads
Emission monitoring (min. 2 sampling points)
Local control panel
Generator circuit breaker for alternator output
External electrical panel for supply isolation
All programming and configuration of the generator and load bank controllers
Platform and ladders
Spare parts for commissioning
Bolt/nut 10% (min. 2 sets)
Gasket 100%
Others : Vendor’s recommendation
Spare parts for Two (2) years (As an Option)
Special tools including programming source for PLC & PLC program loader
lifting eyes and screw jacks required for installation, operation and maintenance
IP inquiry
switchboard- IP42-indoor
MV,LV motor- IP55- indoor
lightign fitting-IP20
junction box IP42
cable gland- IP55
genset IP32 or IP55
control cabinet-IP32
Generator
Bottom cable entry, if not need IP67