671101-000-01-PM-04 Install Wireways, PS06 - Seems to be covered under…
671101-000-01-PM-04
Install Wireways
PM-04-PS01
Undertake risk assessment in accordance with all statutory requirements
PM-04-PS02
Read and interpret electrical drawings
PM-04-PS03
Plan and prepare the worksite set-up
PM-04-PS04
Confirm the selection and installation method of the selected wire ways
PM-04-PS05
Use installation tools and equipment
PM-04-PS06
Design and install wire ways
PA0601: Design the layout of wireways
PA0602: Install wireways
PA0603: Terminate and join the wireways
PA0604: Install wireway accessories
PA0605: Bond wireways
PA0501: Use Tools, Materials and Equipment
PA0502: Use Personal Protective Equipment
PA0401: Design the layout of wireways
PA0402: Select correct conduits, trunking or cable ways for installation
PA0406: Operate drills, cutters, or crimping tools correctly, safely and effectively
PA0403: Select and use the correct personal protective equipment
PA0404: Select and apply the method of installation
PA0405: Select and use hand tools and measuring instruments for installation
PA0407: Install conduits, trunking, trays and ensure correct joints, terminations, and bonding
PA0408: Install, wire, and connect distribution boards, contactors, motors, and control systems
PA0409: Install wireway accessories
PA0410: Bond wireways
PA0411: Terminate and join the wireways
PA0301: Compile a list of tools, material and equipment required
PA0302: Compile a list of human resources required
PA0303: Compile a workflow diagram
PA0201: Identify signs and symbols
PA0202: Read and interpret electrical drawings
PA0102: Identify the hazards.
PA0103: Relate the risk to the hazard.
PA0101: Conduct a preliminary risk assessment.
PA0104: Conduct mitigation of the risk
PS06 - Seems to be covered under PS04.
PS05 - Seems to be covered under PS04.