CONTINGENCY PLANNING
Material Delay
Critical Task
Prevention
Establish long-lead materials, early.
Pre-qualify more than one vendor.
Mitigation
Fast-track procurement.
Approved substitutions.
Dedicated Supply-chain / Logistics .
Recovery
Prepare a catch-up schedule.
Update base-line Schedule.
Non-critical Tasks
Prevention
Track vendor progress in the 3-week look-ahead schedule.
Mitigation
Adjust task logic and re-sequence works to absorb delays.
Recovery
Monitor float utilisation.
Manpower Delay
Critical Task
Prevention
Having in-house labourer of various activities.
Apply a roster system of on-call or contract workers.
Maintain standby subcontractor pool.
Track daily productivity targets.
Mitigation
Mobilize backup teams.
Apply overtime/ shift work as per regional labour laws.
Reallocate skilled resources.
Recovery
Review manpower variance daily and update manpower logs.