Ship Loose Material Control, Inspections, Load Out Preparation,…
Ship Loose Material Control
KOM
14-Oct
High level Schedule
Eng’g team to advice the ideal location for integ. ship-loose on the modules
Due Date: 21-Oct
:check:
Integration work material identification
Due Date: 24-Oct
:check:
Indicate ID (Tag) no. on the material
Due Date: 07-Nov
:check:
Store small items in a box
(such as inst. Bolt & nuts.)
Due Date: 07-Nov
:check:
List / picture / mapping work
Due Date: 18-Nov
Store the box and pallet in the container
Look the Key of the Containers (Start C/C) - 10-Nov
Issue of invoice
(export)
00-Nov
Inspections
Custom Clearance
Finish: 14-Nov
Start: 12-Nov
MWS Walkthrough (All Modules)
Finish: 19-Nov
Start: 17-Nov
Load Out Preparation
Wash Down + Dismantle + Final Paint
P3P00
10-Nov
:check:
P5P00
13-Nov
P1P00
13-Nov
Shiploose Loading Completion
P3P00
P5P00
P1P00
Wash Down + Photo and Video
P3P00
P5P00
13-Nov
P1P00
14-Nov
Weighing Modules
P3P00
11-Nov
:check:
P1P00
15-Nov
:check:
P5P00
16-Nov
:check:
Lifting Module
P1P00
17-Nov
P5P00
17-Nov
P3P00
Remove Keel Block
11-Nov
:check:
Move the Mod. (Assembly Area 3 to Road 4) by SPMT
12-Nov
:check:
Lifting by Floating Crane
13-Nov
Pad Eye NDT After lifting
P1P00
18-Nov
P3P00
14-Nov
P5P00
18-Nov
Demobilization and Preparation for Sail Away
19-Nov
Sail Away
20-Nov-2025 :tada: :tada:
Official Load Out Schedule updated: 30-Nov-25