BSR
CCC
031
WTR(Utilities- Water System)
032
STM(Utility - Steam Generation)
033
CWU(Utility- Cooling Water)
035
PIA(Utilities -Plant and Instrument Air)
036
NDU(Utilities - Nitrogen Plant)
037
FGS(Utilities - Fuel Gas System)
039
CAUS(Utilities - Caustic Supply)
040
ELEC(Utilities -Electrical Power Generation)
A_4001A
(Utilities - Boiler A-4001A)
A_4001B
(Utilities - Boiler A-4001B)
A_4001C
(Utilities - Boiler A-4001C)
A_4001D
(Utilities - Boiler A-4001D)
057
FS(Offsites - Flare System)
058
ET(Offsites - Effluent Treatment)
059
FWS(Offsites - Fire Water System)
002
(INTC)
GEN
(General Facilities)
ADM_GEN (Admin Building)
CCC_GEN
JCC_GEN
M1_GEN
M2_GEN
P1_GEN
P4_GEN
P6_GEN
PP_GEN
SCC_GEN
P6
018
SWS(Sour Water Stripper)
019
ARU(Amine Regeneration)
020
CNU(Spent Caustic Neutralization)
022
SRU(Sulphur Recovery Unit)
024
LCO(Hydrotreater Unit)
025
SRU2(Sulphur Recovery Unit 2)
BMA
G1
G11
G12
G2
OMA
M1
038
FOS(Utilities - Fuel Oil System)
051
RT(Offsites - Refinery Tankage (excluding Product Tank Farm))
054
PB(Offsites - Product Blending)
055
FO(Offsites -Flushing Oil)
056
SLOP(Offsites -Slops)
P4
011
CDU(Crude Distillation)
012
NTH(Naphtha Hydrotreater)
013
CCR(Continuous Catalyst Reformer)
014
KTU(Kerosene Treatment)
023
ISOM(Isomerization)
M2
034
SWI(Utilities - Seawater Intake)
055
FO(Offsites -Flushing Oil)
060
CT(Crude Tankage)
082
SPM(Single Point Mooring)
P1
015
RFCC(Residue Fluid Catalytic Cracking)
016
LTU(LPG Treatment)
017
NTU(RFCC Naphtha Treater)
021
PRU(Propylene Recovery Unit)
SCC
052
PFP(Product Tank Farm)
053
TL(Truck Loading)
JCC
081
MF(Marine Facilities)