Township Project: Detailed Work Breakdown Structure (WBS), OMKAR MOZE …
Township Project: Detailed Work Breakdown Structure (WBS)
1.0 Project Management & Pre-Construction
1.1 Project Planning & Design
1.1.1 Feasibility Studies
1.1.1.1 Market Analysis & Demand Assessment
1.1.1.2 Technical Viability & Site Suitability Study
1.1.1.3 Financial Feasibility & Return on Investment (ROI) Analysis
1.1.2 Master Plan Development & Site Layout
1.1.2.1 Zoning and Land Use Planning
1.1.2.2 Traffic Flow and Circulation Design
1.1.2.3 Green Space and Amenity Planning
1.1.3 Architectural & Engineering Design
1.1.3.1 Conceptual & Schematic Design
1.1.3.2 Detailed Architectural Drawings (Floor Plans, Elevations, Sections)
1.1.3.3 Structural Design & Analysis
1.1.3.4 MEP (Mechanical, Electrical, Plumbing) System Design
1.1.4 Cost Estimation & Budgeting
1.1.4.1 Preliminary & Detailed Bill of Quantities (BOQ)
1.1.4.2 Cash Flow Projections and Funding Schedules
1.1.5 Project Scheduling
1.1.5.1 Master Schedule Creation (using Gantt/PERT charts)
1.1.5.2 Milestone Definition and Critical Path Analysis
1.1.6 Procurement & Contract Management
1.1.6.1 Vendor Prequalification and Selection
1.1.6.2 Tender Document Preparation and Floating
1.1.6.3 Contract Negotiation and Award
1.2 Permitting & Approvals
1.2.1 Land Use & Zoning Permits
1.2.2 Environmental Impact Assessment & Clearances from Pollution Control Board
1.2.3 Building Plan Sanctions & Permits from Municipal Authority
1.2.4 Utility Connection Approvals (Power, Water, Gas)
1.2.5 Fire Department No Objection Certificate (NOC)
1.2.6 Aviation Authority Clearance (if applicable)
1.3 Site Preparation
1.3.1 Site Survey & Topographical Mapping
1.3.1.1 Boundary Demarcation and Staking
1.3.1.2 Contour & Level Mapping
1.3.2 Geotechnical Investigation (Soil Testing & Analysis)
1.3.3 Site Clearing, Grubbing & Demolition (if required)
1.3.4 Temporary Site Infrastructure
1.3.4.1 Fencing, Hoarding & Security Cabin Installation
1.3.4.2 Construction of Temporary Access Roads
1.3.4.3 Establishment of Site Office, Storage & Labour Camps
1.3.4.4 Provision of Temporary Utilities (Water, Electricity for Construction)
2.0 Residential Buildings (5 Towers - 3BHK, 10 Towers - 2BHK)
2.1 Substructure (Foundation)
2.1.1 Excavation & Earthwork
2.1.1.1 Marking and Layout of Foundation
2.1.1.2 Mass Excavation and Soil Disposal
2.1.1.3 Trenching for Footings and Utilities
2.1.2 Shoring & Piling (If required by soil conditions)
2.1.3 Foundation Footings & Raft
2.1.3.1 Formwork (Shuttering & Staging)
2.1.3.2 Steel Reinforcement (Rebar cutting, bending, and fixing)
2.1.3.3 Concrete Pouring & Curing (Including quality control tests)
2.1.4 Foundation Waterproofing & Damp Proof Course (DPC)
2.1.5 Backfilling & Compaction in layers
2.2 Superstructure (Frame & Walls)
2.2.1 Structural Frame (Columns, Beams, Slabs)
2.2.1.1 Formwork Installation for Vertical Members (Columns)
2.2.1.2 Reinforcement & Concreting of Columns
2.2.1.3 Formwork Installation for Horizontal Members (Beams & Slabs)
2.2.1.4 Reinforcement & Concreting of Beams & Slabs
2.2.2 Masonry & Walls
2.2.2.1 Brickwork / Blockwork
2.2.2.2 Lintel & Sill Construction
2.2.2.3 Internal Plastering (Wall preparation and application)
2.2.2.4 External Plastering (Including waterproofing compounds)
2.3 Building Envelope (Exterior)
2.3.1 Roofing System
2.3.1.1 Structural Roof Deck Installation
2.3.1.2 Thermal Insulation Laying
2.3.1.3 Multi-layer Waterproofing Application
2.3.2 External Wall Cladding / Façade Work
2.3.3 Installation of Windows, Ventilators & External Louvers
2.3.4 Installation of External Doors (e.g., Balcony, Terrace)
2.3.5 External Painting (Surface preparation, primer, and multiple coats)
2.4 MEP Services (Mechanical, Electrical, Plumbing)
2.4.1 Plumbing & Sanitary Works
2.4.1.1 First Fix: Concealed Piping for Water Supply & Drainage
2.4.1.2 Pressure Testing of all pipelines
2.4.1.3 Second Fix: Installation of Sanitary Fixtures (Toilets, Basins)
2.4.1.4 Final Fix: Installation of CP Fittings (Taps, Showers)
2.4.2 Electrical Works
2.4.2.1 First Fix: Conduit Laying in Slabs & Walls
2.4.2.2 Second Fix: Wiring, Cable Pulling, and Switchboard Installation
2.4.2.3 Final Fix: Installation of Switches, Sockets, and Light Fixtures
2.4.2.4 Earthing & Lightning Protection System Installation and Testing
2.4.3 Fire Fighting & Safety System
2.4.3.1 Sprinkler System Piping & Installation
2.4.3.2 Fire Hydrant & Hose Reel Installation
2.4.3.3 Installation of Smoke Detectors and Fire Alarm Panel
2.4.4 HVAC (Ventilation)
2.4.4.1 Installation of Exhaust Fans in Toilets & Kitchens
2.4.4.2 Ducting for common area ventilation
2.5 Interior Finishes
2.5.1 Flooring
2.5.1.1 Waterproofing in Wet Areas (Toilets, Kitchens)
2.5.1.2 Screeding and Leveling
2.5.1.3 Tiling (Vitrified, Ceramic) & Grouting
2.5.1.4 Skirting and Threshold Installation
2.5.2 Wall Finishes
2.5.2.1 Internal Painting (Surface preparation, Primer, Putty, Paint)
2.5.2.2 Dado Tiling in Kitchens & Toilets
2.5.3 Ceilings
2.5.3.1 Ceiling Plastering & Painting
2.5.3.2 False Ceiling Installation (if any)
2.5.4 Doors & Windows
2.5.4.1 Installation of Internal Door Frames & Shutters
2.5.4.2 Installation of Door Hardware (Locks, Handles, Stoppers)
2.5.5 Carpentry & Joinery
2.5.5.1 Kitchen Platforms & Cabinets
2.5.5.2 Wardrobes and Loft Storage
2.6 Common Areas & Services
2.6.1 Lobbies & Corridors Finishes (Flooring, Painting, Lighting)
2.6.2 Staircase Finishes & Railing Installation
2.6.3 Elevator Installation, Testing & Commissioning
2.6.4 Common Area Lighting and Signage
3.0 Educational & Public/Commercial Buildings
(The detailed tasks from Section 2.1 to 2.6 would be adapted and applied here, with considerations for specialized requirements such as acoustic treatments in classrooms, laboratory fittings, reinforced flooring for commercial spaces, or specialized HVAC systems.)
4.0 External Utilities & Services
4.1 Water Management
4.1.1 Filtered Water Supply Network (Piping, Valves, and Metering)
4.1.2 Unfiltered Water Supply Network (for landscaping, etc.)
4.1.3 Underground & Overhead Water Tanks Construction
4.1.4 Water Treatment Plant (WTP) Installation and Commissioning
4.2 Drainage & Sewage
4.2.1 Sewage Disposal Network (Piping, Manholes, Inspection Chambers)
4.2.2 Sewage Treatment Plant (STP) Installation
4.2.2.1 Civil Works for STP tanks
4.2.2.2 Mechanical & Electrical Installation for STP
4.2.3 Storm Water Drainage Network (Piping, Drains, Collection Pits, Rainwater Harvesting)
4.3 Power & Communication
4.3.1 Electrical Substations & Transformer Installation
4.3.2 Main Electrical Cabling & Distribution Network (Trenching & Laying)
4.3.2 Main Electrical Cabling & Distribution Network (Trenching & Laying)
4.3.4 Street Lighting Installation and Automation
4.4 Gas Supply
4.4.1 Piped Gas Supply Network & Metering Stations
5.0 External Development & Landscaping
5.1 Roads & Pathways
5.1.1 Roadway Earthwork (Cut & Fill) and Subgrade Preparation
5.1.2 Sub-base & Base Course Laying and Compaction (GSB, WMM)
5.1.3 Asphalt / Concrete Paving
5.1.4 Footpath & Pathway Paving
5.1.5 Curb Stones & Road Markings, Signage Installation
5.2 Gardens & Landscaping
5.2.1 Hardscaping (Walkways, Patios, Seating Areas)
5.2.2 Softscaping (Topsoil Spreading, Grading, Planting)
5.2.3 Irrigation System Installation (Sprinklers, Drip)
5.2.4 Installation of Garden Fixtures (Benches, Lights, Water Features)
5.3 Sport Facilities
5.3.1 Court/Field Preparation & Leveling with proper drainage
5.3.2 Surface Finishing (e.g., Synthetic court surface, natural turf)
5.3.3 Fencing, Netting & Lighting
6.0 Project Closeout
6.1 Testing & Commissioning
6.1.1 Comprehensive testing of all MEP systems (Plumbing, Electrical, Fire)
6.1.2 Final Inspection & Snagging (Punch List creation)
6.1.3 De-snagging and Rectification Works
6.1.4 Final Joint Inspection with Client
6.2 Documentation & Handover
6.2.1 Obtaining Occupancy & Completion Certificates
6.2.2 Preparation and submission of As-Built Drawings
6.2.3 Compiling and handing over all Operation & Maintenance Manuals
6.2.4 Handover of Project to Client/Facilities Management, including all warranties, manuals, and keys.
6.2.5 Final Site Cleanup and Demobilization of all temporary structures.