🧠3.4 Project Scope, Deliverables and Structure
3.4.1 identify / review project deliverables .
Measures
• Knows and uses goal prioritization.
• Considers the organisation's existing project planning procedures
• Considers standard PBS if they exist
• Knows and explains the difference between goals, deliverables and tasks.
• Organizes associated goals and deliverables
• Defines project deliverables and represents them as PBS
• Knows the principle of interactions between PBS and WBS
• Verifies the completeness of the PBS from the results of the WBS and vice versa (Consistency)
• Uses Agile software for structuring deliverables when using Agile planning methods
3.4.2 Structure project tasks and milestones.
Measures
• Considers the organisation's existing project management procedures
• Considers standard WBS if they exist
• Knows and explains the purpose and benefits of structuring project tasks
• Knows the uses of a WBS
• Knows and applies the principles of creating a WBS
• Knows the different decomposition criteria that can be used to build the WBS
• Knows the purpose and principles of coding a WBS
• Explains the consequences of the differences between the construction rules of a WBS
• Explains the limitations of the project and can give examples
• Arguments why and when a detailed WBS may be inappropriate when applying Agile methods to project management
• Uses project management software for entering WBS data and formatting results
3.4.3 Define or identify project work packages .
Measures
• The overall success criterion of an effective work organisation structure.
• The possibility of defining the data that characterize the task or Work package of tasks (duration,resources).
The definition of a work package or a task mainly includes (non-comprehensive list):
• The summary description of the work to be carried out
• The objectives of the work package in terms of identifiable result in the PBS
• The WBS coding
• The defined duration or the dates of execution
• Resource allocations
• Workloads and/or costs.
3.4.4 Organize the integration of different project schedules.
Measures
• Reliability of schedule
• Definition of the milestones necessary for the synchronization of schedules
• Harmonization of resource structures
• Harmonization of progress management methods
• Common coding rules
• Common rules for editing documents
• Standardization of units
• Implementation of computerized management systems able to integrate and consolidate the
different levels of stakeholder plans
• Establishment of consolidated dashboards
• Harmonization of workflows
3.4.5 Contribute to establish and manage project configuration .
Measures
• Manages or participates in the management of the product configuration(s)
• Participates in the development of configuration management roles and responsibilities
• Aligns configuration dependency with the overall project goa
• Defines the product configuration(s)