Work breakdown structure
Engineering and construction work
1.1 Pre-Construction Survey (30 days)
1.2 Prepare Preliminary Construction Work (28 days)
1.3 Prepare Detailed Design (35 days)
1.4 Engineering and Construction Work Report Compilation (45 days)
Cost evaluation
2.1 Evaluate Construction Cost (21 days)
2.2 Evaluate Operation Cost (including staff training) (14 days)
2.3 Evaluate Maintenance Cost (14 days)
2.4 Total Cost Report Compilation (21 days)
staff hiring and training
3.1 Develop Requirements for Hiring Staff (14 days)
3.2 Evaluate Staff Training Requirements (7 days)
3.3 Develop Training Procedures (20 days)
safety certification
4.1 Gather Local Reclamation Safety Standards and Regulations (21 days)
4.2 Overseeing the Certification Process (30 days)
4.3 Liaising with Authorities to Achieve Certification (60 days)
site preparation
5.1 Site Tendering (30 days)
5.2 Site Development (60 days)
civil structures
6.1 Civil Structures (60 days)