Project Added to Database, Design Teams CCTV,CX,Alarm, Security Manager,…
Project Added to Database
Design Required
Yes
SiteOwl Design Creation
Merch Print
A1 Print
VMS Export
Floor plan
Any additional details
Scope Review & Assignment to Firm:
(90-120 Days Pre-Possession)
Add SM and MAPM to Design
Notice a Design Has Started
Provide Communication with FAQ's
Design Review & Walkthrough:
( 65-90 Days Pre-Possession)
Set Meeting with Stakeholders
30 Minute Walkthrough of Design
Review/Add/Change
Update Database - Design Completed
Provide Bid Package to SM
Added to SiteOwl project for review
No
Security Manger Submits Major Equipment and Labor POs to VMO(65-58 Days Pre Possession)
Contract Specialist Places Purchase Orders into SAP(Between 58-50 Days Pre Possession
VMO Updates Database with Confirmation POs Issued
STAR Receives POs and Begins the Equipment Delivery Coordination with Install Vendor (Occurs 50 Days Pre Possession)
STAR Ship Date and Transit Time (Occurs 15 Days Pre Possession)
Star On-Site Equipment Delivery (Delivery Occurs 5 Days Pre Possession)
Installation Starts on Possession Date
Security Manager Updates Database