Project Life cycle - Coggle Diagram
Project Life cycle
Assigned Leader SPOC
sales engineer, Application and Execution
WIN 1
sales engineer, Application, engineering, proposal meeting with Leader SPOC
-
WIN 2
-
WIN 3
Proposal will be ready, Feasibility study of the project execution
-
Probability of the project will be informed by the leader SPOC on discussion with the application & sales & Execution engineer
-
WIN 4
-
WIN 4 process call for the Engineering team - mechanical, electrical, instrumentation, Insource SPOC will be part of this meeting
Resource Planning,
Engineering estimation hours,
Read various proposal document prepared
-
-
-
DOR between client, veolia, vendor
-
Proposal deveolopment folder
- GPC
- Customer contract
- Final Proposal
- deviation list
- quotes
- selected vendor for proposal estimation
- schedule
- package estimation ( bill of material, cost, equipment warranty, spare, flight charge, special lubricant if any)
- proposal ITP to be checked
Transfer package meeting
During transfer package meeting each item listed in the proposal development folder to be reviewed for each package
MDL preparation
Estimation workflow, DRM, EEP, PEP to be prepared
Internal Kick off meeting to be planned.
All SPOC and one person from PE office to be part
PEP should be signed by DN
- 1 more item...