MDL APPROVAL, MMS test, 1w, 1w, 2d, 2d, 2w, 1w, 2d, 1w, 2d, 1m, 3w, Create…
MDL APPROVAL
Folder Link
Request Station IP
Switching number
Conceptual Drawing Approval
Schemetic Drawing approval
Panel Installation
Tester
-CID File
SI
-SCD Compilation
SI
BCU Logic
Typical
SI
MMS testing
Point Test
Interlock Test
Typical
SI
Full Bay
WI Test
SCD Submission
Tester
Typical
-MMS
-ITP
Tester
Full Bay
-MMS
-ITP
SCD Upate
Folder Link Update
DV
1 more item...
Designer
Drawing Swap
Production
Panel and Label Check
Fiber Optic installation
Request Fiber Optic
Operation Setting ?
MMS test
1w
1w
2d
2d
2w
1w
2d
1w
2d
1m
3w
Create Check list
Print
Typical ITP
Typical WI
Conceptual
Schemetic