Please enable JavaScript.
Coggle requires JavaScript to display documents.
Kitchen Renovation - Coggle Diagram
Kitchen Renovation
Level 2
Material Procurement
2.6) Order Placement
2.7) Financing arrangement
2.5) Supplier selection
2.8) Delivery Schedule Coordination
2.4) Evaluation
2.9) Storage & Inventory Management
2.3) Request for quotations
2.10) Material utilization planning
2.2) Supplier Research
2.1) Material Requirement identification
Level 4
Construction and Installation
4.1) Utility Installation :
4.1.2) Plumbing Work
4.1.3) HVAC Work
4.1.1) Electric Work
4.2) Floor Installation
4.3) Install Cabinet and Countertop
4.4) Appliance Installation
4.4.2) Microwave
4.4.3) Dishwasher
4.4.1) Oven
4.4.4) Refrigerator
4.4.5) Heat Collector
4.4.6) Sink
4.4.7) Lighting
4.5) Painting and Finishing
4.6) Backsplash Installation
4.7) Final Inspection and Closeout
Level 3
Demolition
3.2) Furniture removal
3.3) Debris Removal
3.1) Establish a demolition plan
3.1.1) Kitchen Survey
3.1.2) Safety measures
3.1.2.1) Secure the premises
3.1.2.2) Utility Disconnection
3.1.2.3) Site Preparation
3.1.3) Removal of all electrical appliances
3.4) Site Cleaning
3.4.1) Recycling or Disposal of waste
3.5) Site Inspection (Post Demolition)
Level 1
Planning and Designing
1.1) Discuss Requirement and Preferences
1.2) Hire a right Professionals
1.2.1) Make a design and drawings
1.2.1.1) Kitchen Design
1.2.1.1.5) Flooring
1.2.1.1.6) Lights
1.2.1.1.7) Electricals
1.2.1.1.8) Panting
1.2.1.1.4) Countertops
1.2.1.1.3) Cabinets
1.2.1.1.2) Fixtures
1.2.1.1.9) Plumbing
1.2.1.1.1) Appliances
1.2.2) Make a base model (3D model)
1.2.3) Cost Estimation and Timeline
1.3) Finalize design plans
1.4) Documentations