Sorted Boxes (Ready to Relocate) by KMD (27 June 2024)
Supervision - 83 boxes (in-progress)
CB - 84 boxes (done list)
ALD - 204 boxes (done list)
TOM - 68 boxes (list in-progress)
Equities - 40 boxes (done list)
Audit - 10 boxes (done list)
Ready to move by 28/6
Investigation (ESU) - 200 boxes
Approach
By box basis
ALD
By file basis
hybrid
Equities file
Equities by box submission
AOB - relocate
AOB by box - dispose
Total boxes = 11,326
Relocated until 3 july = 1,391 boxes
Balance as at 3rd july = 9,935 boxes
No of days of relocation required = 50 days
constraint = 200 boxes per day
No of weeks of relocation required = 10 weeks due to constraint of 5 working days
Expected completion date = 13 sept 2024
cost normal box (including percentage)
cost for odd sizes boxes (including percentage)
price vs quantity