6th FLOOR, BED-ROOM (6th Floor), 2 BED-ROOM(6th Floor), 2 BED-ROOM(6th…
6th FLOOR
Corridor
-
-
SFD
100% remaining ,doors not available at site
Glass
-
-
EL-1 100% remaining, due to no labour
-
BED-ROOM (6th Floor)
BED ROOM
Ceiling board 70% completed, one large room remaining ,lift and material room
-
-
-
-
Skirting 80% complete , due to doors , windows and 1 large room
-
WASHROOM
Ceiling board 80% completed , 20% remaining due to MEP
-
-
-
2 BED-ROOM(6th Floor)
BED ROOM
Ceiling board 100% remaining ,sub contractor labour not avaailable
-
-
-
Skirting 80% complete , due to doors , windows and 1 large room
Ceiling putty 100% remaining ,
WASHROOM
Ceiling board 80% completed , 20% remaining due to MEP
-
-
-
2 BED-ROOM(6th Floor)
BED ROOM
Ceiling board 100% remaining ,lift and material room
-
-
-
-
-
-
-