5th FLOOR, A-APT(5th Floor), B-APT(5th Floor), CA-APT(5th Floor), CB…
5th FLOOR
.
Corridor
-
-
-
-
Glass
-
-
-
EL-1 100% remaining, due to no labour
-
A-APT(5th Floor)
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
B-APT(5th Floor)
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
CA-APT(5th Floor)
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
CB-APT(5th Floor)
ROOM
-
-
Wooden Doors 60% Completed ,40% remaining due to floor tiles
-
-
Skirting 60% complete , due to doors anf floor tiles recently completed
-
DA-APT(5th Floor)
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
DB-APT(5th Floor)
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
DC-APT(5th Floor)
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
DD-APT(5th Floor)
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
EA-APT(5th Floor)
ROOM
Ceiling board 100% remaining ,ceiling not available
-
Wooden Doors 100% Remaining , lift area
wall primer ok 100% ,putty remaining
-
Skirting 95% complete , due to doors
-
EB-APT(5th Floor)
ROOM
-
-
Wooden Doors 100% remaining ,due to floor tiles
-
-
Skirting 60% complete , working in progress
-
FA-APT(5th Floor)
ROOM
-
ceiling 1st Paint ok 70%, remaining 30% 1 room not ok . working start in 2 days
-
Walls 1st Paint 70% ok , remaining 30%, 1 room not ok . working start in 2 days
-
Skirting 95% complete , due to doors
-
FB-APT(5th Floor)
ROOM
-
ceiling 2nd putty ok 100% , paint started
Wooden Doors 50% remaining , sub contract labour missing
-
-
Skirting 95% complete , due to doors
WASHROOM
-
Floor tiles 90% complete , 1 washroom remaining
-
Wall tiles 90% complete , 1 washroom remaining