2nd FLOOR, A-APT, B-APT, CA-APT, CB-APT, DA-APT, DB-APT, DC-APT, DD-APT,…
2nd FLOOR
.
Corridor
-
-
-
SFD
90% completed, EA apt remaining due to lift
Glass
-
-
-
EL-1 100% remaining, due to no labour
-
A-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
B-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
CA-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
CB-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
DA-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
DB-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
DC-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
DD-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
EA-APT
ROOM
-
Wooden Doors 40% remaining , install in 2 to 3 days
-
-
Skirting 95% complete , due to doors
-
EB-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
FA-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-
FB-APT
ROOM
-
-
-
-
-
Skirting 95% complete , due to doors
-