A-APT ( 1st FLOOR, B-APT, CA-APT, CB-APT, DA-APT, DB-APT, DC-APT, DD-APT,…
A-APT ( 1st FLOOR
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
-
Skirting 80% complete , due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
B-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
-
Skirting 80% complete , due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
CA-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
-
Skirting 80% complete , due to doors
-
CB-APT
ROOM
-
-
-
-
-
Skirting 80% complete , due to doors
WASHROOM
Ceiling board 100% remaining, not available
-
-
-
DA-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
-
90 % ok Skirting, 10% remaining due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
DB-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
-
90 % ok Skirting, 10% remaining due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
DC-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
-
90 % ok Skirting, 10% remaining due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
DD-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
-
90 % ok Skirting, 10% remaining due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
EA-APT
ROOM
Ceiling board 100% remaining ,lift room area
-
Wooden Doors 100% remaining ,not present at site
-
Floor Tiles 100% remaining ,lift room
-
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
EB-APT
ROOM
-
ceiling putty 100% remaining , due to airtech office
Wooden Doors 100% remaining ,not present at site
-
-
90 % ok Skirting, 10% remaining due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
FA-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
Floor Tiles 90% ok ,10% remaining , dismantling area ,tiles not available at site
90 % ok Skirting, 10% remaining due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
FB-APT
ROOM
-
-
Wooden Doors 100% remaining ,not present at site
-
Floor Tiles 90% ok ,10% remaining , dismantling area ,tiles not available at site
90 % ok Skirting, 10% remaining due to doors
WASHROOM
Ceiling board 100% remaining ,Board not available
-
-
-
1st Floor
Corridor
-
-
-
SFD
SFD 99% Remaining , install soon
Glass
-
-
-
EL-1 100% remaining, due to no labour
-