Ground Floor, CA-APT, CB-APT, A-Apt, B-APT, STAIR CASE-1, STAIR CASE 2,…
Ground Floor
Corridor + Foyer Area
-
-
-
-
Glass
-
-
-
EL-1 100% remaining, due to no labour
-
CA-APT
-
-
-
Ceiling Board 100% remaining ,due suspension system and MEP
-
-
-
CB-APT
-
-
-
-
-
Wooden door 100% remaining ,doors not availabledoor
-
-
B-APT
Washroom
-
Ceiling
Ceiling Board 100% remaining ,due suspension system and MEP
-
-
-
-
STAIR CASE-1
-
-
-
wall +slab 1st Paint ok , 2nd paint remaining
-
STAIR CASE-3
-
-
-
wall +slab 1st Paint ok , 2nd paint remaining
STAIRCASE-4
-
-
-
wall +slab 1st Paint ok , 2nd paint remaining
FA-APT
Room
-
2nd coat Wall putty ok , paint not ok due to material present (Paint + Walls
-
Tiles 80 % complete ,20% remaining due to not tiles available at site
Wooden Doors 100% remaining ,not present at site
Skirting 90 % complete , 10% remaining due to floor tiles and floor tiles
WASHROOM (FA-APT)
-
Wall Tiles 90% complete, remaining due to not present floor tiles
-
Floor Tiles 100% remaining, not present at site
DC-APT
ROOM
Ceiling Board 100% remaining ,due suspension system and MEP
-
Wooden door 100% remaining ,doors not available
-
-
-
-
DD-APT
ROOM
Ceiling Board 100% remaining ,due suspension system and MEP
-
Wooden door 100% remaining ,doors not availabledoor
-
-
-
-
EB-APT
ROOM
Ceiling Board 100% remaining ,due suspension system and MEP
-
Wooden door 100% remaining ,doors not available
-
-
-
-
FB-APT
WASHROOM
-
-
Ceiling Board 100% remaining ,not present at site
-
.
ROOM
-
-
-
100% remaining .not present at site ,Wooden Door
-
-
skirting 90 % complete ,remaining due to walls and floor tiles
-
Cainteen- APT
ROOM
Ceiling Board 100% remaining ,due suspension system and MEP
-
Wooden door 100% remaining ,doors not availabledoor
-
Floor Tiles 100% remaining ,
-
-
-