Causes of Project Delays
Design
Underestimating amount of work
Unexpected problems (learning in innovative projects)
Risks
Low risks that end up as a big issue
Wrongly (or not) identified risks
Inefficient design process (unnecessarily redoing design-work)
Late feedback
From project team
From customer
Best design concept/solution not defined
No divergence done
Team
PT not working as team but as individuals
test
Labo test
Test engineer not available
Prodcution problems have priority
Field issues have priority
No back up if test engineer is out (holidays, sick leave,...)
Bad test results
Due to unknown solutions (innovation)
Due to ambitious performance targets (LAT, noise, ...)
Field test
Late field feedback
Units sent to the field too late
Units not used in the field
Prototype build-up
Parts not available
People not available (fitters)
Lack of information during build-up
Lack of instructions
Lack of support from designer/PL/TE
Release
Underestimating the time to make 2D drawings
Inefficient approach
Lack of preparation
People not available (holidays...)
CA's stuck in other departments
Underestimating work of approvers in different departments
Other priorities
Procurement
Dealays at supplier side
Miscommunication with suppliers
Lack of prototype suppliers
Master Spec
Unclear targets
Master Spec signed too late
Targets changing during project
Master spec too detailed
Endless discussions on exact phrasing
Limited opportunity to find new solutions