FHI Major Projects - Laceration Injury

People

Workplace

Management

Work Environment

Live airport operations which involved delays, work pauses and other interference

Physical work layout/ conditions were within a trench which is a confined space

Work environment was restrictive due to scope of works being conduit installation which involved trench excavations, pipe installation, sand etc. all moving in a small area

Individual factors

Worker operating grinder was experienced, trained, competent and compliant with all inductions and associated documentation such as signing onto SWMS

Individual was wearing all required and appropriate PPE

Individual was aware of a more suitable tool available for use; however, proceeded with grinder

Individual was initially unaware that they wer contacted by an object and sustained a deep/ serious laceration

Training/ Competencies

The individual required an online and onsite induction which was completed and on record

The individual required a general Construction Induction Card which was on file

The individual possessed an electricians qualification

There was no history of previous medical incidents or cases for the individual

Systems Organisational Management

process

ADBSFG have their own process for installing conduits which was applied for the scope of works

Standard/ general practice according to ADBSFG is that sandbags are placed over the end of the conduits to highlight the end. This did not occur when the incident took place.

A reciprocating saw is generally used and known to be the more suitable tool for cutting conduit within a trench which was not used.

Job Design

The job was planned to occur throughout the day instead of night, despite the interference from ongoing/ live and operational aircraft movements

Potential external workload pressures were involved to finish the job, or keep progressing due to the number of delays from organisational factors, such as airport interference etc.

Job requirements

An excavation permit was required for the conduit installation which was issued and followed through the correct process

Two SWMS, FH and ADBSFG (Principal Contractor and Subcontractor) were required for the works which were reviewed and signed by all involved workers before activities commenced.

'Work as Done' vs 'Work as Imagined'

It was expected or intended for approximately 120m of conduit and trenching would be completed throughout the day however only roughly 70m were being completed per day.


This may have contributed to workplace pressures/ stress.