CAPM equations
Default
PV
PV = BAC x % (should be done)
EV
EV = BAC x % (is done atm)
AC
Variances
Cost variance
CV = EV - AC
Schedule variance
SV = EV - PV
Indexes
Cost performance index
CPI = EV / AC
Schedule performance index
SPI = EV / PV
To-Complete Performance Index
eTCPI
(BAC - EV) / (EAC - AC)
bTCPI
(BAC - EV) / (BAC - AC)
Estimates
Estimate to complete
ETC = EAC - AC
Estimate at completion
EAC = BAC / CPI