Project Management

A project is a set of activities with a defined start point and a defined endpoint, which pursues a defined goal and uses a defined set of resources.

Most operations improvement (even continuous improvement) can be seen as a series of overlapping mini-projects that cumulatively contribute to a never-ending development effort

Project Commonality

All projects are missioned focused – they are dedicated to achieving a specific goal that should be delivered within a set timeframe, to certain specifications, using defined group resources

project management is the activity of defining, planning, controlling, and learning from projects of any type

It is concerned with balancing what the project delivers, the time it takes, and its costs within the so-called iron triangle (quality, time, and cost)

This is a very broad activity in that it can encompass almost all the operations management tasks (this is in the context of operations development because the majority of projects that the manager will be engaged in are essentially improvement projects)

Programmes vs Projects

Programmes, such as continuous improvement programmes, have no defined endpoint. Rather, it is an ongoing process of change

Individual projects may be individual sub-sections of an overall programme, but programme management will overlay and integrate the individual projects

Differentiating by project's volume and variety characteristics

All project processes are, by definition, in the top left corner of the matrix, but, within that end of the natural diagonal, projects do vary

At the very top, left-hand of the matrix are projects that are genuinely first-timers, with a very high degree of uniqueness, a volume of one and an infinite variety

With less uniqueness, higher volume, and less variety (as before, but…) projects may share some of the attributions of previous projects but may have new features where project managers have little or no previous experience to help guide them

With higher volume (therefore a greater degree of repetition) and lower variety (paint by numbers), projects are relatively routine and predictable, and so, more straightforward to manage

Differentiating by project's scale, complexity, and uncertainty characteristics

a wedding planning project has (relatively) low levels of scale, complexity, and uncertainty.

management challenges of such a project are significantly different to developing the Airbus A380, which exhibited much higher levels of all three dimensions (the scale, complexity, and uncertainty of such ground-breaking projects demand far more sophisticated planning, greater and more flexible resources, and careful control if they are to be successful)

stages of Project Management

Stage 1 = Understanding the project environment – internal and external factors that may influence the project

Stage 2 = Defining the project – setting the objectives, scope, and strategy for the project

Stage 3 = Project planning – deciding how the project will be executed

Stage 4 = Technical execution – performing the technical aspects of the project

Stage 5 = Project control – ensuring that the project is carried out according to the plan

Project environment

This comprises all the factors that may affect the project during its life

The factors are considered as:

  1. Geo-social environment – geographical, climatic, and cultural factors that may affect the project
  1. Eco-political environment – economic, governmental, and regulatory factors in which the project takes place
  1. Business environment – industrial, competitive, supply network, and customer expectation factors that shape the likely objectives of the project
  1. Internal environment – individual company’s or group’s strategy and culture, the resources available and the interaction with other projects that will influence the project

Role of Stakeholders

Project stakeholders are those individuals, groups, or entities that have an interest in the project process or outcome. In other words, they affect or are affected by, the project

Types:

Internal stakeholders include the clients, the project sponsor, the project team, functional managers, contractors, and project support

External stakeholders (this includes those outside of the core project, rather than necessarily outside of the organisation) include end users, suppliers, competitors, lobby groups, shareholders, government agencies, and employees

Managing stakeholders

One approach to discriminating between different stakeholders is to distinguish between their power to influence the project and their interest in doing so

Categories:

High-power, interested groups must be fully engaged, with the greatest effort made to satisfy them

High-power, less-interested groups require enough effort to keep them satisfied, but not so much that they become bored or irritated with the message

Low-power, interested groups need to be kept adequately informed, with checks to ensure that no major issues are arising. These groups may be very helpful with the detail of the project

Low-power, less-interested groups need monitoring, though without excessive communication

Project definition

Its objectives – the end that project management is trying to achieve

Its scope – the exact range of the responsibilities taken on by project management

Its strategy – how project management is going to meet its objectives

Project definition continuation

Objectives

help to provide a definition of the endpoint, which can be used to monitor progress and identify when success has been achieved

They can be judged in terms of the five performance objectives (quality, speed, dependability, flexibility, and cost)

However, flexibility is regarded as a given in most projects, which, by definition, are, to some extent, one-offs.

Speed and dependability are typically compressed into one composite objective – time

Leads to the Iron Triangle (Cost, Time, and Quality)

Good objectives are that that are clear, measurable and, preferably, quantifiable

Clarifying objectives involves breaking down project objectives into three categories

Purpose – to allow budgets to be agreed upon and confirmed prior to the annual financial meeting

End result – a report that identifies the causes of budget delays, and recommends new budgeting processes and systems

Success criteria – the report should be completed by 30th June, meet all departments’ needs and enable integrated and dependable delivery of agreed budget statements. The cost of the recommendation should not exceed $200,000

Scope

It is a boundary-setting exercise that attempts to define the dividing line between what each part of the project will do and what it won’t do

Defining scope is particularly important when part of a project is being outsourced

A supplier’s scope of supply will identify the legal boundaries within which the work must be done

Sometimes the scope of the project is articulated in a formal project specification, which is the written, pictorial, and graphical information used to define the output and the accompanying terms and conditions

The project scope will also outline limits or exclusions to the project

This is critical because perceptions of project success or failure often originate from the extent to which deliverables, limits, and exclusions have been clearly stated and understood by all parties during the scoping phase

Strategy

defines, in general rather than a specific way, how the project is going to meet its objectives

This is done by:

defining the phases of the project

setting milestones and/or stage gates

Milestones is a more passive term, which may herald the review of a part-complete project or mark the completion of a stage

A stage gate often launches further activities and, therefore, commits the project to additional costs etc

How can projects be planned?

The planning process fulfils four distinct purposes:

It determines the cost and duration of the project

It determines the level of resources that will be needed

It helps to allocate work and to monitor progress

It helps to assess the impact of any changes to the project

The process of planning is:

Identify the activities in the project (the work breakdown structure)

Estimate the times and resources for activities

Identify the relationships and dependencies between the activities

Identify time and resource schedule constraints

Fix the schedule for time and resources

Process of Planning continuation

IA

Most projects are too complex to be planned and controlled effectively unless they are first broken down into manageable portions, which is achieved by structuring the project into a family tree that specifies major tasks or sub-projects

In turn, these are divided into smaller tasks until a defined, manageable series of tasks, called a work package, is arrived at

Each work package can be allocated its own objectives in terms of cost, quality, and time.

They also:

Don’t exceed 10 days

Should be independent of each other

Should belong to one sub-deliverable

Should constantly be monitored

Leads to the work breakdown structure (WBS), which brings clarity and definition to the project planning process

ET&R

The impact of uncertainty on estimating times leads some project managers to use a probability curve to describe the estimate

These are usually a positively skewed distribution, showing the greater the risk leading to a greater range of distribution

The natural tendency of some people is to produce optimistic estimations, but these will have a relatively low probability of being correct because they represent the time that would be taken if everything went well

A Pessimistic estimate assumes that almost everything that could go wrong does go wrong

Expected activity time = Te = (to+ 4tl + tp) / 6

Variance = ((tp - to )^2) / 36

te = Expected activity time

to = Optimistic activity time

tl = Most likely activity time

tp = Pessimistic activity time

IR&D

All the work packages that are identified will have some relationship with one another that will depend on the logic of the project

Some activities will, by necessity, need to be executed in a particular order, such as building a house

Whilst other activities do not have any such dependence on each other, such as the rear garden of the house, could probably be prepared totally independently of the gauge being built

A Gnatt chart is the simplest way to exhibit an overall project plan, because they have excellent visual impact and are easy to understand.

These two activities have an independent or parallel relationship

ISC

The finite nature of critical resources – such as special skills – means that they should be taken into account in the planning process

This often has the effect of highlighting the need for more detailed re-planning

Fundamental approaches

Resource-constrained – When only the available resource levels are used in resource scheduling and are not exceeded. As a result, the project completion may slip

Time-constrained – The overriding priority is to complete the project within a given time. Once normally available resources have been used up, alternative threshold resources are scheduled

FS

Network Analysis

As a project’s complexity increases, it becomes necessary to identify clearly the relationship between activities and show the logical sequence in which activities must take place

Bitrix24, Trello, 2-Plan PMS, Asama, MS project, and Producteev

This is typically done using the critical-path method (CPM) to clarify the relationships between activities diagrammatically (activity-on-node method)

The diagram shows that there are a number of chains of events that must be completed before the project can be considered finished

The longest of these chains of activities is called the critical-path as it represents the shortest time in which the project can be finished and therefore dictates the project timing

However, non-critical activities have some flexibility as to when they start and finish (known either as float or slack)

Program Evaluation an Review Technique

This is a technique that recognises that activity duration and costs in project management cannot be forecasted perfectly, so probability theory should be used

In this type of network, the duration of each activity is estimated on an optimistic, a most-likely, and a pessimistic basis

If it is assumed that these times estimations are consistent with a beta probability distribution, the mean and variance of the distribution can be estimated as follows

te = (to+ 4tl + tp) / 6

The variance of the distribution (V) can be calculated as follows:

V= ((tp - to)^2) / 6^2

Project control

deals with the management activities that take place during the execution of the project. As such, project control is the essential link between planning and doing

This involves 4 key challenges

How to monitor the project in order to check on its progress

How to assess the performance of the project by comparing monitored observations of the project with the project plan

How to intervene in the project in order to make the changes that will bring it back to plan

How to manage matrix tensions in the project in order to reconcile the interest of both the project and different organisational functions

Project control continuation

Project monitoring

To some extent the measures used will depend on the nature of the project. However, common measures include:

Current expenditure to date

Supplier price changes

Amount of overtime authorised

Technical changes to project

Inspection failures

Number and length of delays

Activities not started on time

Missed milestones

Some of these monitored measures affect mainly cost, some mainly time. However, when something affects the quality of the project, there are also time and cost implications

Assessing project performance

The monitored measures of project performance at any point in time need to be assessed so that project management can make a judgement concerning overall performance

This pattern of a slow start followed by a faster pace, with an eventual tail-off of activity, holds true for almost all projects, which is why the rate of total expenditure follows an S-shaped pattern

Intervening to change the project

If the project is clearly out of control in the sense that its costs, quality levels, or time are significantly different from those planned, then some kind of intervention is almost certainly likely to be required

The exact nature of the intervention will depend on the technical characteristics of the project, but it is likely to need the advice of all the people who would be affected

Given the interconnected nature of projects – a change to one part of the project will have knock-on effects elsewhere – which means that interventions often require wide consultation

Managing matrix tensions

In all but the simplest projects, project managers need to reconcile the interests of both the project itself and the departments contributing resources to the project

To function effectively, matrix management structures should have the following characteristics:

There should be effective channels of communication between all managers involved, with relevant departmental managers contributing to project planning and resourcing decisions

There should be formal procedures in place for resolving the management conflicts that do arise

Project staff should be encouraged to feel committed to their projects, as well as to their own department

Project management should b seen as the central coordinating role, with sufficient time devoted to planning the project and securing the agreement of the line managers to deliver on time and within budget