1000KVA - Prime power- PTSC MC - Coggle Diagram
1000KVA - Prime power- PTSC MC
hồ sơ đóng 12 Jan 2024
thời gian thực hiện: IV-2023 đến IV-2024
300 days delivery
Origin:
engine, altenator, controller, ACB: EU/G7
container 20 feet: DNV2.7-1: Asia
Environment:
0 to 45 C
salty out door
Engine
Radiator:
anti salt spray
Muffler: spark arrestor
exhaust vent: rain cap stainless steel
Fuel tank:
7 hours
transfer pump, hose
level meter
digital indicator
level switch
drain
material: SS304
Coating and painting for offshore environment
Alternator
50/60hz
PMG
IP 23 ( or 44)
insulation H, temp rise F
coating and painting for offshore environment
Control panel
IP55
SS304
Generator shutdown ESD trip signal ( de-energized to trip, 24V output from PTSC's control system
ACB
rating 2000A
4 poles
IEC 60947-2
IP40
lighting protection
Enclosure
E stop- 2 buttons ( enclosure + panel), IP67
20 feet, ISO 668: 2020
DNV 27.1
IP23
Corner Fittings: 4 Pcs; ISO 1161 – 2016 for carrying container by semi-trailer.
2 door/ side; locking bar/ door
Fixed ladder hidden enclosure
Cable access entry dimensions: 420 x 260mm
Carbon steel, min 2mm thickness
Painting and Coating:
NORSOK STANDARD M-501: 2022
Yellow – RAL 1023
fire protection class A-30
stainless steel 304 plate mesh
lifting lug, bolt and nut for floor installation Certified by third party
Forklift pocket
Lighting/lamp: Dual LED tube light IP65, length 600mm. Qty ; 2 pcs/ side. With 2 switched poles - IP66.
Two (2) earthing bosses
Cable
configuration of parameters by software
All internal cables shall comply with IEC 60502 and IEC 60332
Cable gland: SS316
Accessories:
DO pump: 30 litters/min, power from gen's battery
fire detector (ultra violet & infrared flame)
Operation log box: A4
Charger 10A
Engine rotation tool
lifting set: rope slings set + shackles : DNV 2.7-1
Document
CO, CQ, 24 months warranty
Generator load test report
Engine test report
Alternator test report
ACB test report
Mill cert for lifting set & shackle
Load test- witness pad eyes, lifting set,rope sling, shackles,
DNV 2.7-1 offshore container certificate
Training - 2 days
OMM + Install manual
Part book
Service manual
Wiring, GA
As built document - offshore container
other tech doc
Altitude and temperature derate tables
Test report
FAT
Alignment shaft coupling testing
Vibration testing.
100% load at least 4 hours.
Full function test, protection
SAT
100% load at least 4 hours.
Full function test, protection
load bank for testing.