MSC YOKOHAMA WENCHONG SHIPYARD, Sanjeev Dagar (MSC Shipmanagement Cyprus)…
MSC YOKOHAMA
WENCHONG SHIPYARD
EGCS
Funnel
Steel - miscellaneous small platforms for access - 11/03
Insulation
Above D-deck - 10/03
Below D-deck - 07/03
Safeties 10/03
Level alarm sensors - 10/03
Lighting - 10/03
FDS sensor - 10/03
CO2 piping - 10/03
Small miscellaneous pipes - 09/03
Coating - 12/03
Pumproom
Main SW line to scrubber piping remaining - 06/03
Pumps location finalized, pipes to be installed - 06/03
WTU pump and piping - 06/03
Engine room
CO2 piping and new sensors - 10/03
GRE Pipework - 10/03
Cable laying & termination - 10/03
Piping 08/03
Cargo Hold #8
Piping - 06/03
Storage & recycle tanks (4)
Sandblasting - 05/03
Coating - 09/03
Shaft Generator
Mechanical completion - 06/03
Electrical (Termination)- 05/03
Commissioning - 12/03
Supply and installation of turbochargers and governors for AE. On critical path, can be delayed upto 12/03
Jackup test to be completed - SKF technician available on 07/03
Windshield
Steel works - 10/03
Coating T/U - 12/03
VFD
Zeme (All other motors) - 10/03
Total Automation - (ER blowers & MCSW pumps)
10/03
Steel repairs
Hatch covers - 12/03
17 out of 50 covers still onboard
ISO sockets - 10/03
Lashing bridge - 12/03
Coating
Accommodation - done
Main deck - 11/03
Cargo hold - 10/03
Container test - 12/03
Forecastle misc Steel repairs- 10/03
Bow thruster room miscellaneous repairs- 10/03
Shell plate repairs - 10/03
Impact due to trimming for BT repairs
Bow thruster installation - 13~16/03
Anchor chain 07~09/03
ER pipe lagging - 12/03
ER final cleaning and painting - 12~15/03
ME 2 units liner renewal - 10/03
Sanjeev Dagar (MSC Shipmanagement Cyprus)