Sports Hall HVAC System Upgrading Project
Removal and dismantling of old HVAC unit system
Installation of new HVAC unit system
Connecting new HVAC unit system to electrical system and refrigerant lines
Install new evaporator coil
Install adequate amount of refrigerant
Isolate power supply
Disconnect Old HVAC System
Safe removal of Old HVAC System
Disposal of Old HVAC System
Performance Testing
Quality Control
Material Inspection & Verification
Workmanship
Safety Inspection
Water Leak Test
Refrigerant Leak Test
Ductwork Leak Test
Electrical Test
Thermostat Testing
Correct placement of equipment according to design plan
Quality Criteria
Code Requirements
Performance verification & tuning
System Balancing & Adjustment
Testing of Airflow
Testing for poor insulation
Planning
Site Assessment
Schematic Diagrams
Equipment Selection
Variable Speed Fan
Thermostats
Ducting & Piping Design
Simulation & Calculation
System & Site Layout Plan
Supply
Installations
Contractors
Sourcing
Materials
Final Inspection & Acceptance
Project Handover
Final Documentation
Smart System Training for SIT Staff
Project Closure Meeting
Feedback From Public
Project Closure Report
Execution
Design
Closure
Inspection
Procurement