Project Development Phase
Appointment of Consultants and Subcon
Consultants
C&S
To design R&D, EW, ESCP, Building Plan
To submit all submission related to Jbt. Kejuruteraan - R&D, EW, Building plan
M&E
To provide compact sub design
To prepare all docs required for SKMM
Town planner
Town planner to consult Majlis (OS/DOE) if EIA is required according these general factors:
Zoning of the project site (depends on the state guideline)
ESA (environmental sensitive area)
SIA and WMP Criteria - Prepare along with EIA if required
Prepare for EIA submission if required (concurrent with layout drawing preparation
To submit all docs to OSC and Jbt Perancang for approval
Design
PV Layout and PVsyst report (Stage 0 drawing)
Topo Layout
Building Plan (if its e-house, need to submit for foundation drawing)
Soil Investigation (Borehole and Mackintosh)
Design team to prepare and finalize all standardize drawings after stage 1 drawings
Earthing and LPS Study preparation by subcon concurrent with stage 1 drawing preparation
Once LPS finalised then proceed to CCTV and street light design
Design team to prepare stage 1 drawings as stated below:
PV Facility Sizing Report
Piling Point
Inverter location
MV & MV Cable Marker
MV Cable Trench
LV Cable & Cable Marker
LV Cable Trench
LV Cable Schedule
DC Cable & Cable Tagging
DC Cable Trench
DC Cable Schedule
KM submission
Jab Kejuruteraan
EW and R&D submission
Agensi Perakuan Bekalan Air (APBA)
SAINS (Optional)
Indah Water Konsortium (IWK)
Online submission for E-SWAP
Jabatan Alam Sekitar (JAS)
EIA approval
Requires R&D, EW, ESCP plan
Need to present GTM and Geotechnical Design report
The zone that is permitted for solar farm development will be for Agricultural and Industrial zones
Jabatan Kerja Raya
Entrance and exit road to project site
R&D infrastructure
Required to built separate drainage to discharge water from project site, cannot be shared with drainage beside JKR main road
Road slope entering the main JKR road cannot exceed 2% for total length of 50m from existing road side. Otherwise, Cattle trap required to be built.
Wash through must be prepared during EW phase
MARRIS form must be filled for the roads within the 'Taman' and for new development.
Jabatan Mineral dan Geosains (JMG)
Geological Terrain Mapping (GTM) report, and Geotechnical design report must be prepared by professional Geologist
Jbt Pengairan dan Saliran (JPS)
Must not develop anything within the buffer zone for the reserved river (10m left & right hand side)
Retention pond must be 4% from the project site area, and it cannot touch the reserved river.
The developer cannot close or transfer any existing river or drainage without JPS approval
Prepare ESCP drawing
Plan Malaysia
The KMTT min duration is 3 years, and max duration is 10 years only
Pejabat Tanah dan Daerah (PTD)
Required to apply for Permit Khas provided the category is under Agriculture and the developer is renting the land
Pejabat Tanah dan Galian (PTG)
Permit khas must be applied if the land usage is less than 1/5 of the land. Otherwise, required to do application dor amendment of terms
Suruhanjaya Komunikasi dan Multimedia Malaysia (SKMM)
Perbadangan Pengurusan Sisa Pepejal (SWCORP)
Require to submit the septic tank design unless its standalone
TNB
Plan must include compact substation
Jbt. Perancangan dan Pembangunan
KM fee and deposit fee
KMTT Permit Tahunan fee (depends on the duration)
Procurement
PVF Equipments
MST supplier - Pass the SI report and Topo layout for them to come out with Technical proposal
IF Equipments
SPPIF
Switchgear, Meter reading Software
DC cable, LVAC cable, MVAC Cable
*once the cable schedule has been finalized by Design team
Interconnector
Underground cable, Overhead cable, Fibre Optic Cable
TNBIF
Switchgear, CRP, RTU, Arc Protection, Metering Panel
Equipment delivery to site
Laydown area must be ready prior material arrive at Port
FAT for the equipment must be done 1 month prior to arrive at site
Prepare procurement tracking list including ETD, ETA, Vessel number
Other Permit and Regulatory Approval Applications
NEDA
Prepare for NEDA submission after project is handed to Project team
GITA
Prepare after NEDA submission
ST
Prepare Financial Model
*Can submit after NEDA, GITA and ROW
ROW
Prepare U-Map, HDD Profile