Atek PC Case Study - Coggle Diagram
Atek PC Case Study
Timeline
PMO's implementation strategy is to work within the culture and to develop forces that will promote the PMO and overcome cultural resistance
The issue of PMO governance wasn't widely discussed, there were no roadmaps/timelines so the strategy is to work within the culture
-
Competing with other PC companies they were forced to implement the PMO due to the dramatic pressure
PMO mission drives for Cost reduction. Also being more creative, adaptive and agile when launching new products
AtekPC realizes they need to implement a more effective project management office by taking an Agile approach.
-
-
-
Relevant Facts
PMO-Light requires less experienced staff, and lower management
-
-
-
-
AtekPC had initially adopted an informal approach to project management with speedy response times however as projects became more complex the informal approach was no longer possible and call for implementation of a PMO was needed.
PMO were divided into two categories, project-focused and enterprise oriented.
-
Possible solutions
-
Research on other ways the company can keep up with the PC industry competition as well lower production costs
-
-
-
Key Problems
-
Push back on PMO
What is the cause?
AtekPC has had an informal approach to project management for a long time and the PMO may require some changes in the way projects are managed in the company. Some employees do not understand the function of the PMO and claim its bureaucratic.
Who is responsible?
The CIO, Director Application Development and other employees
-
-
How did it happen?
In an effort to cope with the increasing competition in the PC industry and to minimize production costs AtekPC management introduced a PMO to provide standardization in managing large and complex scale projects.
-
What is the consequence?
The PMO is mostly focused on IT projects and is facing challenges as it tries to move to other departments (Enterprise).
-