Mobile 35 in service (10/6/22 -10/25/22) - Coggle Diagram
Mobile 35 in service (10/6/22 -10/25/22)
Mobile #35 in service
Establish Clearance on 115/12kV Bank A at Cleveland (GTC)
Clearance Points:
Removal Date (10/25/22)
Sign off Bank A clearance
Establish Line Clearance to remove HS connections
Establish clearance to remove LS Mobile Cables and temporary Jumpers between H7141 and H7143.
Establish Clearance on Mobile #35 to pack up and ship out
Install Date (10/05/22)
115kV Connections
Close 115kV NO switch to source from Tallulah Lodge
Tap HS to 115kV Line
Need Line Clearance on 115kV line from South Cleveland to Cleveland (GTC) to make connections to Mobile 35.
12kV Connections
Clearance to connect LS mobile Cables to Disconnect H7143
Add Jumpers from H7143 to H7141
Cover up exposed section of 12kV Main bus for construction to install PTs
Pre-Work
Pre-work at Cleveland (GTC)
Grading & Fence Work
Pre-work: Test Engineering
Switching
Submit Work Requests
Create Power Point for Switching Plan
Contact Keith Ridgeway (GSOC) about writing switching for Mobile Install
Distribution
Determine who is the local GPC Engineer
Contact Local GPC Distribution to verify they are okay to run unregulated during main bus outage.
Create a Work Plan (016)
Scope, Risks/Mitigations, Time Line