WORKPLAN EXE 2.PG 24
The transport cost is R1000, the overhead cost…
WORKPLAN EXE 2.PG 24
The transport cost is R1000, the overhead cost is 10% per unit and the percentage profit to be added is 35%, show the calculations of the cost price and the selling price per unit, Calculate the trade discount of 8%, (Do not round off)
-
STEP 2:
-
Overhead cost is 10% per unit, therefore one must find out 10% out the unit price of R2 840.88
-
-
-
-
-
-