TTMS Terms of Payments - SCC Section C Page 154 - Coggle Diagram
TTMS Terms of Payments - SCC Section C Page 154
(A) Advance Payment
-
10%
of
Entire Contract Price
)
Exclusive of all Recurrent Costs
Paid against receipt of a claim accompanied by the Advance Payment Security specified in GCC Clause 13.2
(B) Recurrent Costs
: to be paid periodically upon delivery of services on monthly interval for the services delivered, on submission and Purchaser’s approval of invoices.
(C) Run the Programme. Programme Management
:
(80%)
of pro-rata Contract Price for this category against Delivery and Approval by the Purchaser.
(10%
) of pro-rata of Contract price at completion of whole project
(D) Change management, Business Readiness and Training, services
(80%)
of pro-rata Contract price shall be paid for Change Management, Business Readiness and Training Services
(10%)
of pro-rata Contract price Shall be paid on
completion of the project
(E) Data Center Facilities supplied, installed & operationalized (DC & DR):
(60%)
of pro-rata Contract Price for this category against
Delivery
and
Approval
by the Purchaser
(10%)
of pro-rata of Contract Price against
Installation
.
(10%)
of pro-rata of Contract Price against
Operational Acceptance
of this category
(10%)
of pro-rata of Contract Price at
completion of whole project
(F) Power supply equipment supplied, installed, and operationalized (DC, DR and Offices mentioned in the roll out plan)
(60%)
of pro-rata Contract Price for this category against
Delivery
and
Approval
by the Purchaser.
(10%)
of pro-rata Contract Price against
Installation
(10%) of pro-rata Contract Price against
Operational Acceptance
of this category
(10%) of pro-rata Contract Price at
completion of whole project
(G) Data Centre Racks & Servers supplied, installed, and operationalized (DC & DR):
(60%)
of pro-rata Contract Price for this category against
Delivery
and
Approval
by the Purchaser.
(10%)
of pro-rata of Contract Price against
Installation
.
(10%)
of pro-rata of Contract Price against
Operational Acceptance
of this category
(10%)
of pro-rata of Contract Price at
completion
of whole project
(H) Local Area and Wide Area Network supplied, installed, and operationalized (DC, DR and offices mentioned in the roll out plan)
(60%)
of pro-rata Contract Price for this category against
Delivery
and
Approval
by the Purchaser.
(10%)
of pro-rata of Contract price against
Installation
.
(10%)
of pro-rata of Contract Price against
Operational Acceptanc
e of this category
(10%)
of pro-rata of Contract Price at
completion
of whole project
(I) Data Centre Private Cloud Management Software supplied, Installed and operationalized (DC & DR):
(60%)
of pro-rata Contract Price for this category against
Delivery
and
Approval
by the Purchaser.
(10%)
of pro-rata of Contract Price against
Installation
.
(10%)
of pro-rata of Contract Price against
Operational Acceptance
of this category
(10%)
of pro-rata at
completion
of whole project
(J) End User Computing (EUC) Devices and related third-party software products supplied and installed (incl Insp Vehicles):
(60%)
of pro-rata Contract Price for this category against
Delivery
and
Approval
by the Purchaser.
(10%)
of pro-rata of Contract Price against
Installation
.
(10%)
of pro-rata of Contract Price against
Operational Acceptance
of this category
(10%)
of pro-rata of Contract Price at
completion
of whole project
(K) Driving License Smart Cards designed, developed and supplied (TO);
(60%)
of pro-rata of Contract Price Contract Price for
work completed as planned per program increment
(20%)
of pro-rata of Contract Price Contract Price
for installed, tested, and working per program increment
(10%)
of pro-rata Contract price at
completion
of whole project
(L) Dev Space working on hosted private cloud (until DC & DR ready to use):
(60%)
of pro-rata Contract Price for
work completed as planned per program incremen
t
(20%)
of pro-rata Contract Price for i
nstalled, tested, and working per program increment
(10%)
of pro-rata Contract price at
completion of whole project
(M) Help Desk Solution integrated into TTMS:
(60%)
of pro-rata Contract Price for
work completed as planned per program increment
(20%)
of pro-rata Contract Price for
installed, tested, and working per program increment
(10%)
of pro-rata Contract price at
completion of whole project
(N) Biometric data management services including integration with automatic biometric information system (ABIS) at NID (PMO) delivered and operationalized
(60%)
of pro-rata Contract Price for
work completed as planned per program increment
(20%)
of pro-rata Contract Price for
installed, tested, and working per program increment
(10%)
of pro-rata Contract price at
completion of whole project
(O) Migrate Data stage 1:
(60%)
of pro-rata Contract Price for work
completed as planned per program increment
(20%)
of pro-rata
Contract Price for installed, tested, and working per program increment
(10%)
of pro-rata Contract price at
completion of whole project
(P) Core and common services software applications
(60%)
of pro-rata Contract Price for
work completed as planned per program increment
(20%)
of pro-rata Contract Price for
installed, tested, and working per program increment
(10%)
of pro-rata Contract price at c
ompletion of whole project