Schedule Management

Planning (5)

Initiating (0)

Executing (0)

Monitoring & Controlling (1)

Closing (0)

1. Plan Schedule Mgmt.

2. Define Activities

3. Sequence Activities

4. Estimating Activity Durations

5. Develop Schedule

Control Schedule

Scheduling software

Scheduling metrics

Scheduling tolerance

Approach

Accuracy level of schedules

Methods

Managing

Controlling

Variances

Agile

Length of releases/iterations

Formats of reports

ITTOs

Outputs

Schedule Mgmt. Plan

Inputs

Tools & Techniques

Scope mgmt. plan

Project Charter

Development Approach

EEFs

OPAs

Expert judgements

Data analysis (alternatives analysis)

Meetings

Work Package-->Activities

Milestones-->0 duration

Activity ≠ Task

ITTOs

Outputs

Inputs

TTs

Activity list

Activity Attributes

Milestone list

Like WBS Dictionary

CRs

Revision in

Schedule baseline

Cost baseline

Schedule Mgmt. Plan

Scope Baseline

EEFs

OPAs

Expert Judgements

Decomposition

Meetings

Rolling Wave Planning

Progressive Elaboration

Network Diagram/Schedule Activity Diagram/Activity Network Diagram ✅

Scheduling duration ❌

3 methods

Precedence Diagramming method (PDM)

Activity on Node (AoN)

Arrow Diagramming Method (APM)

Activity on Arrow (AoA)

Graphical Evaluation & Review Technique (GERT)

image

Start-to-start (SS)

image

Finish-to-finish (FF)

image

Start-to-finish (SF)

image

LAG

image

LEAD

image

Dependency Type

Hard Logic (Mandatory)

Soft logic (Discretionary)

External

Internal

Preferred way

Draw Network activities

Assume Finish-to-start (FS)

For Scheduling calculations

2 type of questions

Predecessors given

Successors given

ITTOs

Outputs

Inputs

TTs

Schedule network diagrams

Revision in

Activity list

Activity Attributes

Milestone list

Assumption log

Schedule Mgmt Plan

Scope Baseline

Activity list & attributes

Milestone list

Assumption log

EEFs

OPAs

Precedence diagramming methods

Dependency Determination & Integration

Leads & Lags

PMIS

Same techniques are used for duration & cost of the activities

Techniques

One point estimating

Analogous estimating

Bottom-up estimating

Parametric estimating

*Three point estimating

Top-down estimating

Similar historical

No calculation

Assembling estimations

Standard metrics

Industry requirements

Other sources

Historical data

Do Calculations

Methods

Regression analysis

Learning curve

Heauristic

3 parameters

Optimistic Estimation

Most Likely Estimation

Pessimistic Estimation

2 distributions

Triangular distribution

Simple/Straight

Beta distribution

Estimated Activity duration (or Cost)=(P+M+O)/3

Weighted Avg/PERT

Estimated Activity Duration (or Cost)= (P+4M+O)/6

Std Deviation=(P-O)/6

↑ Std Dev--↑ Risk

If distribution is not mentioned, assume Beta distribution

Important Points

Padding

Extra time /cost to estimation

NOT ALLOWED

3 point estimating helps!

Estimated Activity Duration

Contingency Reserves for Risk

Law of diminishing returns

image

Experience, capability & resources count

Technology used

Team motivation

ITTOs

Outputs

Duration estimates

Basis of estimates

Constraints, assumptions, risks

Trust level of estimates

Range estimations

Revisions in

Activity attributes

Assumptions log

Lessons Learned Register

Inputs

Schedule Mgmt Plan

Scope Baseline

Activity list & Attributes

Assumption log

Lessons Learned Register

Milestones list

Resources

Project team assignments

Resource breakdown structure

Resource Calendar

Resource Requirements

Risk Register

EEFs

OPAs

TTs

Expert Judgements

Estimating Techniques

Data Analysis

Alternatives analysis

Reserve Analysis

image

Decision making tools

Voting

image

Meetings

Schedule Network Analysis

a) Critical Path Method

b) Schedule Compression

c) Monte Carlo Analysis

d) Resource Optimization

e) Agile Release Planning

Path where any delay will cause delay in total project duration

Float/Slack: Other activities can get delayed without affecting proj duration

Float=0

Total float

Free Float

Project float

Without affecting project duration

Without affecting successor's early start date

Without affecting target Proj duration

Calculations

Start of day notation ✅

End of day notation

image

image

image

Search for better options

Fast tracking

Crashing

By rearranging the activities

To run them in parallel

Increasing/adjusting the resources

What if both fast tracking/crashing can't be chosen??

Reduce Scope

Cut Quality

Simulation

S Curve

Resource smoothing

Resource Levelling

Proj duration/delay is NOT considered

Proj duration is considered

ITTOs

Outputs

Project schedule

Network Diagrams

Bar/Gantt chart

Milestone charts

Schedule baseline

Schedule data

Project Calendars

CRs

Revision in

Schedule mgmt. plan

Cost baseline

Resource requirements

Duration estimates

Activity attributes

Assumption log

Lessons learned register

Risk register

Inputs

Schedule mgmt plan

Scope Baseline

Activity attributes & Activity list

Assumption log

Durations estimates

Basis of estimates

Lessons learned register

Milestone list

Proj schedule network diagram

Resource Calendar

Resource Requirements

Agreements

EEFs

TTs

CPM

Schedule network analysis

Resource optimization

Data analysis

What if

Simulation

Leads & Lags

Schedule compression

PMIS

Each iteration=1 feature

Agile release planning

ITTOs

Outputs

Work performance information

Schedule forecasts

CRs

Revision in

Schedule mgmt plan

Schedule baseline

Cost baseline

Perf measurement baseline

Basis of estimates

Resource Calendars

Project schedule & schedule data

Risk register

Lessons Learned register

Inputs

Schedule mgmt plan

Schedule baseline

Scope baseline

Perf mgmt baseline

Lessons Learned Register

Proj Calendars & Resource Calendars

Proj schedule & schedule data

Work Performance data

OPAs

TTs

Data analysis

Earned value analysis

Perf reviews

Trend analysis

Variance analysis

What-if analysis

Iteration Burndown Chart

CPM

PMIS

Resource Optimization

Leads & Lags

Schedule Compression