CML3 documentation - Coggle Diagram
CML3 documentation
-
-
-
SUMMARY
-
Construction breakdown
-
16/02/2020 Ground: settlement, D=1.5m hole, filled with sand-cement
-
-
-
-
Mitigation 1.1
-
-
-
-
23/02/2020 Hyperbaric intervention: lower bentonite level in bulkhead -> materials on other side of gate
17/02/2020 Slurry circuit: back-fllush, pipes pop, risk of further damage
Mitigation 1.2
Date?? Soil investigations (cored borehole, destructive boreholes, geophysical survey)
-
-
-
-
-
Date?? New trials to unclog valves + Investigations of surface + nearby utilities disconnected -> trenches are excavated
-
-
-
-
-
-