Increase in Civil Cost
Change in scope
External impacts
Increase in raw material costs (June'20 to March'21)
Cost escalations due to COVID impact (Value wise big contributor)
due to delay in inputs to Contractor
Delay in Engineering drawing approval
GE Considerations during tender
Change in Customer requirements ( Engineering To come with evidences during next call to validate)
Overstay compensation at site due to increase in schedule (Original Commissioning Nov'20, Now changed to June'22)- ~40lacs (Value wise big contributor)
Ex: no of fire walls were considered as 3 against normal practise of 5. Drawing ref:
As per normal practice and Optimum solution, For AC filter banks (capacitors, Reactors, BPI, CT, disconnectors, resistors etc) isolated foundation were considered but during execution as Electrical inputs were delayed, to expedite construction works it was decided for Common slab (Record of agreement / Change management available?) which requires additional cost of 2 to 5 times- Not considered for further drill down as this was not due to wrong considerations during tender? to check with Electrical Tender lead
Delay in Schedule- To mitigate timelines it was decided to go with Common slab
Engineering inputs delayed for individual equipment's
No.of foundations increased (170 considered during tender and in actual it is coming to 259 equipment foundations)- To check if requirements was validated by Engineering during Tendering (to check as sold EA sheet/ Rohit / Shradha+ What are the foundation actually increased leading to this BDR
Civil Engineering Lead during Tender??
Electrical Lead during Tender?? (Value wise big contributor)
Additional works due to Site conditions to support constructability and erection activities. ( Extra work in rail cum road, rerouting of cable trenches, additional road works)
Why delay in Engineering inputs?- Anil
CT, disconnectors, resistors documentation was not approved while this decision was taken Anil to share our submission and customer comments data (Dates and comments)
Rework at site due to Wrong considerations (in TCR yard (Near TCR reactor for BPI) equipment structures / foundations should be free from Magnetizing effect)- Ahmad/Ambuj
Area considered for gravel spreading was less than the actual area required (Value wise big contributor)
Increase in Control building size
Road length has increased from 825sq.m to 1103sq.m)
Fence length has increased from 550 to 616 sq.m)
Drain length has increased from 240 to 255sq.m
Cable trench has increased from 635 to 873m
PGCIL Changed the design of filter (7th Filter to 5th / 7th Filter) from what has been agreed during tender? and after initial drawings approval after raft casting in OCT'20 (No impact as it was decided to cast Raft. If individual foundations were taken in to consideration then there will be price escalation due to rework)
Filter design changed during detailed Engineering (7th Filter to 5th / 7th Filter). Not inline with Tender agreement? (No impact as it was decided to cast Raft. If individual foundations were taken in to consideration then there will be price escalation due to rework) Due to common raft price escalation due to Individual foundations and increase in 40 foundations is mitigated
PGCIL was requesting inline with what has been agreed in tender, However Our internal considerations were different
PGCIL was requesting inline with what has been agreed in tender, However Our internal considerations were different
Layout change? Anil to provide the deviation