Commissioning plan - Coggle Diagram
Commissioning plan
Systems
Mechanical systems
Electrical systems Incl Substation
Plumbing systems
Life safety systems
BMS and PMS
Building enclosure
As required by sustainability certifications
ICT Systems
Security systems
Aim
General information about the project
Identify systems to be commissioned
Outline the commissioning process activities
Documentation requirement
Commissioning team members
Describe roles and responsibilities
Commissioning process
Y1-Factory testing
Yx Early testing
Y2-Delivery and installation
Y3-Static testing
Y4-Pre functional testing & Functional testing
Y5 IST
Introduction
YONDR Metro block blue print design
Can be modified with project specific requirement
Objective
Communicate
Key steps
Deliverables
Identify roles and responsibilities
Live document
Will be updated regularly
Purpose
Quality focussed process
Enhancing delivery of a project
Verify and document
Building, Engineering services
Planned
Designed
Installed
Tested
Confirmed
They perform as per
Design document
Owner's requirements
Local building codes
Additional confirmation
Operation & Maintenance
Design Document
Owner's requirements
Remote commisisoning
Advantages
Low cost
Avoid travel constraints
Technologies
Cameras
Robotics
Live streams
Activities
Design Phase
Review of Owner's project requirement by CxPM
Review of BOD by CxPM
From Commissioning prospective
Review of Stage 3 drawings
Commissioning planning
Coordination meetings and workshops
Progress reports and MOM
Commissioning plan
Plant dependency schedule
Commissioning program
Commissioning specification
Response to RFI
Submittal and SOO review before design review
Commissioning software
Issue resolution log
Method statement and test script tracker
CxPM and Vendors
Load bank plan
Temporary service Commissioning plan
Pre functional test scripts
CxPM and Vendors
Functional test scripts
CxPM and vendors
IST plan
Tag templates
Construction phase
Y1 Factory testing phase
Factory witness testing
Factory acceptance testing
Yx Early testing
Prefab at Factory and Complete Y2 Tag
Early pre functional and Functional testing