ENGINEERING SURVEYING

TRAVERSE

EARTHWORK (AREA & VOLUME CALCULATION METHOD)

SETTING OUT

LEVELLING

SUSTAINABILITY & ENVIRONMENT ISSUES IN LAND RECLAMATION PROJECT

DETAIL SURVEY

INSTRUMENTS

TERMINOLOGIES

SUMMARY

TYPE

LINK TRAVERSE

EXAMPLES image image image

METHODS

Angular Misclosure

Total required angle = (Final forward bearing - Initial back bearing) + (m * 180 degree)

*where :

m is an integer, in most cases, m will be (n-1) or n or (n+1)

n is the no. of left-hand angles observed

note : value of m is obtained by assuming that observations are gross-error free

Angular Misclosure & Angle Adjustment

Calculate :

Latitude and departure

Linear misclosure and adjustment of latitude and departure

Forward bearing

Coordinates of certain stations

Angular misclosure and Angular correction

Initial back bearing and final forward bearing

Forward Bearing Calculation

Latitude/departure calculation (Linear misclosure 1:10,000)

Latitude/departure correction (Linear misclosure 1:10,000)

Latitude/departure adjustment (Linear misclosure 1:10,000)

Coordinate calculation

CLOSE TRAVERSE (LOOP)

EXAMPLES image image

METHODS

Angular Misclosure (AM)

The observe angles can be internal/external angles

AM are found by comparing the sum of the observed angles with one of the following theoretical values :

Internal angles required = (2n - 4) * 90 degree

External angles required = (2n + 4) * 90 degree

*where n is the no. of angles measured

Linear Misclosure

Latitude/departure correction

Latitude/departure adjustment

Latitude/departure calculation

Coordinate calculation

Area calculation (coordinate method)

OBJECTIVE

To establish the horizontal control points for uses in detail survey

To act as a preparation for the land reclamation

EQUIPMENT

Total Station

Tripod

Prism

OBJECTIVES

To find treasure point (unknown point) based on coordinate given

To perform the calculation of traverse on the spot when the fieldwork is done

To apply the concept of link traverse in searching the exact location of the traverse

EQUIPMENT

Tripod

Total station

Prism

OBJECTIVES

To carry out Rise and Fall method of booking the reading of levelling in the field

To adjust and apply correction for levelling data

To establish the reduce level

To establish the vertical control and reduce level for station that are involved in traverse at the project area

Measuring tape

Automatic level

Base plate

Levelling field book

Staff

Staff bubble

Tripod

INTRODUCTION

MSL vary with locations due to wind,
current and tides

The most accurate method in
determining height

In Malaysia tides are observed at 21 tidal gauge stations distributed throughout the country in order to obtain the MSL

Heights are based from the mean sea level (MSL) level (MSL) - normally referred to as normally referred to as datum

Reduced Level (RL) – the height of a point
relative to a datum

Bench Mark (BM) – permanent markers with accurate reduced levels. In Malaysia Terminologies these are provided by JUPEM

Temporary Bench Mark (TBM) – temporary markers established normally near construction sites. In particular if site is too far from a BM

The first reading/observation is the backsight whereas the last observation is the foresight

Any other readings/observations contained between the backsight and foresight are called intermediate sights

Only backsights and foresights are used when flying levels (i.e. when determining a when flying levels (i.e. when determining a TBM or BM.)

Intermediate sights are only to be used when the RL of other points are needed

NOTES

Backsights and final foresights must be made to a point with known RL, such as, BM or TBM

Points that are to be TBM or BM must not be observed as intermediate sights – this is to ensure that systematic errors are minimised (will be explained later)

METHODS

Two peg test

Booking and reduction of levels

Rise and fall method

Height of plane of collimation (HPC) method

Inverted staff

INTRODUCTION

Horizontal control was obtained from traverse
survey

Vertical control was obtained from levelling.

A detail survey is used to determine and locate the features and improvements on a parcel of land in which a further detail of a location can be determined

OBJECTIVE

Prism

Tripod stand

Total station

Prism with pole

METHOD

Offsets or trilateration (ties) - only provide horizontal positions. If reduced levels are neede then, levelling is required

Radiation (angle & distance)

Radiation by Tacheometry

Radiation by EDM/Total Station

Details are measured from a control point (station) that is closest to the area to be mapped

provide hori & verti distances at accuracies suitable for detail surveys

Distances obtained by tacheometry are of low order accuracy, therefore, is suitable to be used for producing plans at scales less than 1 : 200

Fieldwork

Select one of the adjacent station as the reference object (RO) and if possible set the horizontal angle to zero ; all angles will be relative to this RO

When the staff is at a point of detail, observe and record the three stadia hairs, horizontal and vertical angles (nearest 1minute is sufficient)

Set-up instrument over station & record the height of instrument (height of the trunnion axis from the ground)

The procedure is repeated for all details needed and as a precautionary measure, it is sensible to check the reading to the RO from time to time

Details are measured either using an EDM mounted on a theodolite or a total station (EDM+theodolite+on-board software)

This method of picking-up details is closely
linked to computer-aided mapping

Recap : EDM is an electronic distance measurement method that is capable of providing horizontal and vertical distances at high accuracies

Data observed are normally entered or downloaded to computers and processed using an engineering surveying software to produce the required plans

INTRODUCTION

Opposite to detail survey.

Setting out is to locate the calculated coordinate of the
things to the ground.

Setting-out is a process of transferring planned project to
the ground by using a suitable method.

OBJECTIVE

Setting out is to locate the calculated coordinate of the
things to the ground.

To execute as-built survey upon the completion of the
setting-out work.

INSTRUMENTS

Prism

Nail

Tripod

Rope

Total station

Measuring tape

INTRODUCTION

Earthwork is a handling and processing
calculation of large of soils and rocks.

Earthwork also used in cutting and filling of earth for basement (car park), underground water tanks, to obtain required formation levels.

OBJECTIVES

Estimate volume of fill and volume of fill material for
reclamation

Estimate the cost of the backfill.

Identify formation level for reclamation area

Identify positive and negative social impact created by the
project.

Identify reclamation impact on environment

METHOD

Spot Height Method

End-Area Method

Setting-out A Circular Curve

Meaning : A process of marking (setting-out) the centre line of a route (road, railway) at chosen intervals

Involves the computations of the deflection angles
from a selected tangent

METHOD

Deflection Angle Method

Transition Curve

How is a transition curve used in road geometric design?

Supposing two straights are connected by a
circular curve

The circular curve is partly replaced by two transition curves at each end (at the beginning and ending sections) as combined curve

Vertical Curves

Needed at intersections of grades or slopes

click to edit

Crest curve - grade meeting at summits

Grades are represented in terms ratio or percentages;
grade 1:40=2.5%

Sag curve - grades meeting at valleys

Rising grades are written as +ve (e.g.+5%)
and those descending as -ve (-5%)

In vertical curve designs, calculations are based on the algebraic difference between gradients

Gradients increasing in the direction of chainage are given +ve sign and those decreasing are -ve

Setting-out A Vertical Curve

How?

The reduced level (RL) of chainage points needed are calculated and pegs/markers are driven to indicate cut and fill

Therefore, setting-out data are chainages whose reduced levels represent the finished level (surface of the proposed road)

EQUATIONS

Length of the curve (2 methods)

Length of curve (2l) based on vertical radial force; 2L (total length) = ((p+q)*(v^2)) / (100f)

The position of the highest point on the
curve from the tangent point;
x = (2p/ p+q) * L

Based on vertical radial force

Based on the sighting distance (S)

Length of curve (2L) based on the sighting distance (S) - 3 cases are possible

S > 2L

S < 2L

S = 2L

Tidal patterns

Wave patterns

River sediment compositions

Abrasion

Slope elevation

Water management area

The change of wave pattern lead to more intensive abrasion

coastal stability becomes low

The tidal wave hit the shore harder than the shock absorbing
mechanism by the sea floor prepared for

become harder

The reclamation activities in the study area reduced the function of the mangrove forest as a natural folder to hold the water excess due to the rain and the up-tide.

The loss of mangrove forests lead to increase of the flooded area then affect the water quality