CROWN LOTUS GROUP - Coggle Diagram
CROWN LOTUS GROUP
BLACK LOTUS COFFEE HOUSE
BLACK LOTUS COFFEE HOUSE : B&D STORE LOCATION
SOFT LAUNCH AUGUST 13TH
RENOVATION
DAY 1 July 19th
Gather Wood in HV & Drop Off to get cut into planks
DAY 4 July 22nd
Finish Kiosk Project (in & out). Water line in, Move Pump. Start Painting Fence White.
Notes: Reach out to Duong for Pump, and line into Kiosk. Upgrade lock system for Kiosk
DAY 5 July 23rd
Complete Painting Fence,
DAY 6 July 24th
Start Metal Work for Log Holder X3
Materials Needed: 3l sheets of metal and regular steel frame, Quality Black Metal Paint
DAY 7 July 25th
Family Day
Bi Mangages completion of Metal Work.
Make sure that frames are Levelled and sealed. Electrical is set up and tested.
DAY 8 July 26th
Complete Metal Work. Set Up Electrical, for Signage.
Materials needed: Led star lights.
Day 9 July 27th
Day 10 July 28th
Day 11 July 29th
Day 12 July 30th
Day 13 July 31st
Day 14 August 1st
Day 2 July 20th
Torch & Stain Logs Tables/Seats, Shop for Full Project Materials
Materials needed: Torch blower, propane tank, Sand paper, silicone fire resistant, foam, strap with crank, Stain warm tone.
Day 3 July 21st
Pick up Wood Planks, 20 x 200. Build Kiosk. Start Metal Work For Kiosk
.
Materials needed: PV glue, Torch, Black Stain, Led warm lights,