Slot Doubler Project Execution
Slot doubler and pile on deck
Grillage fabrication completed
Issue PO for Sea fastening
Approve CTR for fab, NDE & Inst
Approve sea fastening design
RIgging procured
Issue PO for Sea fastening
Vessel arrives port
Vessel on hire
Slot Doubler Ready for load out
Install deployment rigging
Procure rigging & rent spreader beam
Issue PO for rental and procurement
Approve revised design and CTR
DIMCON approved
Issue PO if previous not valid
Review As-Built DIMCON
Mobilize MT to site
Mobilize team to OTC
Approve personnel
MPL to advise MT
Issue PO for metrology scope
Ship equipment
Issue PO for Metrology Scope
Suction pump on site
Ship it and pick-up
Issue PO
Code the item in SAP
Focal point assigned by C&F