MS Topic 1 REFUSE DISPOSAL SYSTEM
Refuse disposal facilities for Residential Buildings
Bin outside private property for waste disposal
Refuse to be collected by licensed collectors
Refuse collected is sent to 4 incineration plant
3 located in Tuas and 1 in Seneko
Process of incineration generated 2-3% of total electricity consumption
non burning and incineration ash are transported to off shore landfill
Pulau Semakau landfill
Refuse chute chamber
Located below a chute and houses a bin
Requirement
Wall to be lined with glazed tiles or impervious material
Floor to be graded to allow waste to flow into gulley
Able to hold 1 day's output of refuse
large enough to house a wheeled refuse bin with cover
Fitted with air-tight non-corrosive flap floor
Refuse Room (For common refuse chute)
Located at bottom of a chute
Houses a large mechanical container
Requirement
Adequate access space for refuse collection vehicle
Wall to be lined with glazed tiles or impervious material
Refuse collected is conveyed directly into refuse collection vehicle
Floor to be graded towards gulley
Large enough to hold 2 days of waste
Water tap to be provided
Refuse disposal facilities for Non-residential buildings
Refuse chutes are not provided in non-residential building
Require cleaner manually collect refuse
Bin centre to be provided when amount of waste exceed 1000litre/day
Requirement for Refuse Bin Centre
Adequate access space for refuse collection vehicle
Bin should be able to hold daily waste output from proposed development
Maintain minimum nuisance and be accessible to refuse collection vehicle
Roofed over and adequately ventilated
Floor to be graded toward gulley
Water tap shall be provided
Wall to be lined with glazed tiles or impervious materials
Refuse Chute
Requirement
control valve located at bottom of chute
Washing and flushing system for whole length of chute
at least 2 ventilated top opening with minimum 0.1m2 each
Cross section area minimum 0.3m2.
individual refuse chute - serve only 1/2 premises per floor
Common refuse chute - serves all premise on same floor sited in a common area
Provide for building taller than 4 storeys