Completed Template Home
PHASE II: PreFab Construction
Construct PreFab Section
Support Side Walls (x2)
Rear Wall
Bedroom Walling Sections (x2)
Roofing Section
Material Treatments
Front Entrance Wall
Material Acquisition
Quality Assessment
Prep for Transportation
PHASE III: House Assembly
Land Plot Preparation
Prefab Transportation
Pour and Set Concrete Foundation
Finalize Structure
Furnishing
HVAC
Electrical Installation
Plumbing
Painting
Prefab Installation
Install Walls
Install Bedroom
Inspection
Quality Inspection
Fire Code Inspection
Building Code Inspection
Welcome Customer to Their New Home
PHASE I: House Contracts
Acquire Land Plot Information from Customer
Record Names and Establish Payment Agreement
Estimate Cost & Duration and Have Customers Sign the Contract