TIS SS Pilot, 22 Feb Update: 2 to 3 iterations. End of March to Middle of…
TIS SS Pilot
Sync Service (Remaining 1 to 2 iterations) Didn't expect speed issues (3 weeks), live defects, holidays
-
-
Email for local office - store in the FE for now, sync through the BE at a later date
-
-
-
-
-
-
-
Monitoring & Analytics (Remaining: 0 to 1 Iteration) - some could be delivered whilst piloting, rather than before we onboard pilot Trainees
-
-
-
Sync Monitoring - for identifying blockages (Pipeline DMS, SQS Quests...)
-
-
Infrastructure (DONE)
POST MVP (thinking IN PROGRESS): Permissions for upload service (does it NEED fixing for MVP, or can be done post-launch? Feeling is it can be done post-MVP - Reval admins might be able to see all Form Rs, but that should be OK)
-
-
-
-
Roll out
-
Trial run the import template (handy as lots of Dev don't have Prod access as yet - so we could do a "real" trial run)
-
-
-
5 Feb: Reviewed progress against estimate - refined estimate to between 1st and 3rd week in March. i.e. Mid-Feb no longer feasible, but (based on reducing the performance challenge with the sync service) mid-March still felt to be the likely completion 'zone'
-
-
-