Scaling Up @ MPH Group Ltd.
Smart Scale Up using Modular, Replicability…
Scaling Up @ MPH Group Ltd.
Smart Scale Up using Modular, Replicability & Speed
A look back......
What if a schedule is prepared to show duration of project lifecycle for various sites. This includes: site acquisition; planning; design / tender; construction; handover; sell / lease
- Gaelarrig
- Millerd St.
- Tivoli Apts
- Sunday's Well
Dennehy's X
- Spinnaker / Driving Range
- Menlo
- Blackrock Cottage
What are our constraints in getting through the project lifecycle in 'normal' timeframe and at initially forecasted costs?
-
Constraints
-
5. Newness of company?Is where we are normal for young company, or is there anything we can do (change) to have less linear pipeline of projects? Or do we establish this over time, with established partners, etc/
6. Our processes? Is there anything we are doing (not doing) that is impacting what we are doing? More defined steps or processes?
7. Our trade partners? Are they delivering what we need and when, across the board? Or the time critical ones anyway?
Constraints
-
2. Capital? Have we capital to progress with a project (planning, tender, construction, etc.)
3. Delays on other projects? That are tieing up capital? And becoming problem children, using up resources?
-
-
-
-