Please enable JavaScript.
Coggle requires JavaScript to display documents.
Project Finance Level 2 - Coggle Diagram
Project Finance Level 2
Level 01 Hooks
-
Risk Allowances
Construction risk
Labour issues, safety hazards, brownfield site
-
-
NRM recommends that risk allowance are not a standard percentage but a properly considered assessment of risk, considering completeness of the design and other uncertainties such as the extent of site investigation undertaken
-
Cost Reporting
-
-
-
What is a cost report
It is a financial report produced at agreed intervals on a project which provides an overview of the client's current financial commitment. The purpose of it is to inform the client of the likely outturn cost of the project, including forecasting the outturn cost as a variance against the budget and/or tender sum. This will give the client an understanding of potential savings or additional monies required
Cost Plan
In the context of cost prediction, RICS professional statement, a cost plan is 'an estimate based on a specific design. A statement showing an apportionment of an estimate or an agreed budget between cost headings'. This would not necessarily be in elemental form. Cost planning is a method of cost prediction
Benefits
1) Designers are aware of the cost implications of their proposals which enables them to arrive at a practical and balanced design
-
-
-
5) The cost plan can act as a value management tool to ensure the client gets a building which meets their needs, but also represents best value
Programme (Prelims)
Preliminaries are typically presented as a weekly rate in developed cost plans; therefore, a programme or at least some high-level dates will be required. The key information usually required is:
1) Design and tendering period
2) Start on site date
3) Construction period
4) Completion date
-
Cost plan risk allowance
A quantitative allowance set aside as a precaution against risks and future requirements to allow for uncertainty of outcome.
-
Change control
-
-
What is change control
Change control is the process of managing and assessing changes to a project and its procedures. Change controls can give a project manager the information they need to regulate projects and alter them based on changing environments, conditions or requirements.
-
-
-
-
Poplar - Forecasting
Cashflow
Cashflow projections
Definition - This is a financial planning tool that shows the predicted flow of cash in and out of a project. This is typically shown month-by-month, for the duration of the project. When the construction phase is underway, the cash flow projection for contractors payments will typically form an 'S curve'.
-
-
Contractor cash flow projections will typically show construction costs, materials, labour, plant, preliminaries etc)
Employer cash flow projections usually consider the project is a much broader context and might include costs such as but not limited to:
-
- Consultant and legal fees
-
- Marketing and sales charges
-
- Employer capital salaries
-
Contractor payments
If the monthly valuations are behind the cashflow projection - This could be an indication that construction works are behind programme
If the monthly valuations are ahead of the cashflow projection - The project is ahead of programme, or the contractor is overclaiming