Contract Practice Level 3
Cobalt - Partial Possession
Practical Completion
2) The 12 month defect period starts
3) The client needs to start insuring and securing the building
1) 50% retention is released, subject to the contract
4) The ability to impose LDs is ceased
Definition - It is called 'practical' completion because it is fit for purpose. The project is sufficiently complete for the employer to take over in that nothing remains outstanding that prevents the employer from using the works, although there may be some outstanding works or defects which remain to be completed
JCT D&B Section 2
Sectional Completion
1) 50% retention is released once each section is complete, subject to contract
2) The 12 month defect period starts on the completed section
LDs are agreed up front for each section
3) The client needs to start insuring and securing the building for the completed section
Definition - Provision within the building contract which allows different completion dates to be set for different sections of the works which have been pre-agreed in the contract
The ability to impose LDs is ceased for the completed section
Clause in the contract - Not in the standard contract but has to be written in
Partial Possession
2) The contractor's responsibility for insuring the works ends
3) The contractor's liability for liquidated damages ends, proportionate to the area of possession
1) 50% retention is released, proportionate to the area of possession
4) Employer becomes responsible for any damages to the works
Definition - Not predefined in the contract but its a mechanism that can be used if the client wishes to take beneficial used of an area on a project before practical completion
5) The defect period commences
JCT D&B Section 2
Poplar - Radiators to underfloor heating
Relevant Matter
Thickening of prelims
Prolongation
Client change to switch from radiators to underfloor heating
JCT D&B Clause 4.21
Relevant Event
Client change to switch from radiators to underfloor heating
4 weeks extension of time granted
JCT D&B Clause 2.26
Reason for the change
Compliance with Part L
Better sequencing of works
More Sustainable