Present to ALT, volume changes, flow through chutes, material changes - how do we achieve 330MT - require new supplier of liners, define a process for WAI, assign new process, materials and invest in achieving the 330MT - 50 problem chutes to move from 40 weeks. Between now and 330MT we have 3 shut cycles (20 weeks) - resources required, investment required to map out the process and invest in the
Identify any critical chutes on the critical belts - create a team that owns the chutes (OS ONLY - Under Improvement) - create a team to work on the strategy
Do the process map, print out all thr drawings, identify the critical chutes, build the WAI process, create the kits, implement the process, manage through Vass and Reliability .