Reporte
Schedule 2020
October 20
Suppliers contracts
PRINS 23/OCT/20
Permits & Licenses
Acceso vial
Remoción línea 13.2 KV
Manejo de vegetación
Gasoduct
November 20
Perimetral roads
Highway access
Platforms
Engeneering integration
Stolze/Prins/VB/Hoogendoorn
Shipping program
Logistic services
December 20
Engineering
Electricity supply
Rain drainage
Sewage & WWTP
Internal Gas network
Internal energy
Water supply
Construction warehouse
Reforestation
Construcción
Almacén no terminado
Piso / Racks / luz
Falta maquinaria
Máquinas Mountain high 2X
Personal inexperto / SB
Instalación de vidrio
Sin equipo adecuado
Schedule 2021
January 21
Packing foundation
Temporary highway access
Perimetral fence
Construction Warehouse
February 21
Foundation pilars 2A
Provisional electric line CFE
Construction team / Ware house keeper, Nurse, Security
Encalado de plataformas
Structure assembling Packing
Medical clinic / COVID protocol
March 21
Bidding internal infrastructure
Engineering of underground piping
Delay in glass transportation
47 containers YTD
Platforms 2A & 2B completed
GH2B
Greenhouse assamblage 2B 200%
Foundation pilars 2B 100%
Underground piping Heating
Service area design (Architectural & Structural)
Arrival of caterpillar platforms
Foundation HST & Boiler room
GH2A
Underground pipe heating
Material dañado
Almacenamiento
Instalación
Condiciones climáticas
Lluvia
Mas grande en 20 años
Sin caminos ni drenajes
Sin acceso al sitio de trabajo
Maquinaria no adecuada
Retraso en el inicio
Material faltante
Robo
Vidrio faltante
Vidrio roto
Almacenamiento
Instalación