PR1-7261
PP1 Second Supply
RFQ
LINK
Requirements
Submission
2 December 2023
Quote - Via Ariba
Highlight
Outline Agreement
Contract
Complex
Hybrid NEC
CV's and Competencies
Construction Line
Items to be
specified in the offer
Risks
Existing Bay Base size
Cable Routing
All eggs in one basket with E&I
Construction
1) Main E&I
Competitive
GLTA
SS
Aurex
Electrical Installation Works
Supply and install Cables
Racking
Earthing
BOQ
PP2 Works
Remove Door
Rig new 11kV Panel into Sub
Re-instate door
Trenching
Include concrete/paving
re-instating
Hard Barricading
Exploratory Digging to Identify existing Trench/Sleeves
Roof Removal
Re-Instating
Mechanical Works
Rigging 40t Trfr out
Rigging Studies with crane and crew
Low Bed for Moving Trfr to stores
Offload Trfr at Stores
Hard Barricade
Rigging new 20MVA trfr In
Rigging Studies with crane and crew
Scaffolding
Trfr Bay @ PP1
PP2 Basement
List of similarly executed projects
References
Construction Methodologies
3) Switchgear Installation ??
Competitive
ABB
CSI via SS
2) F.O Installation
Sole Source
Interconnect
2 X FO
Netw Switches
5) Transformer Assembly
OEM
Assembly and Site Testing
4) Trfr Decommission
Competitive
Siemens
LH Marthinussen
Oil Handling and disassembly
6) Busducting
Competitive
ABB
CSI via SS
Site establishmentr
Mobile Site Workshops
Mobile Site offices
On-site Storage facilities
Ablution facilities
Laydown area
Power Supply for Site Establishment
Engineering
Electrical
In House
Trfr Spec
Cable Routes
Execution Philosophies
11kV Switchgear
Studies
Civil
1) Nako
Partners
Cable Routing
Scanning
Trfr Bay Evaluation
2) Commissioning
Support
Independant
PTS?
End Of Job
Procurement
1) 11kV Switchgear Panel
OEM
ABB SERV
11kV Panel
SMU615 relay
2) 20MVA Trfr
Competitive
Actom Power
Zest WEG
CG Holdings
SGB Smit
NER - Free issued in trfr bay
3) Busducting
OEM
ABB DBN
4) SMU & Integration
Scope
New 11kV MV Panel for PP2
New 20MVA Trfr for PP1
Cabling between PP1 & PP2
F.O Cables PP1-PP2
New Busducting at PP1
Remove existing unused trfr from Trfr Bay
Load Shedding Integration
NER Free Issued
Schedule
MV Panel Installation
Sept 2023 Shut
12 Weeks Lead time - Manufacture
New Trfr
9 Months lead time
Trench Timing
July 2023-Oct 2023
Shutdown Site Offices
Area Occupied
Transformer and Ducting
Anytime
Execution Plan
1) Detail Design (Long Leads)
Jan 2023
Appoint TRFR Manufacturer
Long Lead Manufacturing
Transformer
9 Months
11kV SG
16-20 weeks ExW
Cables
8-12 Weeks
Appoint E&I Sub Contractor
Appoint SG Supplier
Detail Design
Execution Philosophies
Mobilise Teams
Aug/Sept 2023
Trenching and Cable installation
Install New Transformer
Commissioning
Feb 2024??
1 more item...
Cable Terminations
11kV Panel Installation
Transformer Rigging Out
Cable Routes
Integration
Commissioning Plans
Health, Safety & Environment
Full 23point SHE File
SHE Execution Plan
HSE Performance (Past 3 years)
Competencies
Medical Surveillance - TBC
Training/competency (CVs)
SHEQ Policy
HSE System Certification
SPSM Audit
Compensation Commissioner Insurance
ISO Certification- 9001,14001 & 45001
Legal Appointments
Subcontractor appointments
Lifting and rigging
Construction
Risk Management system
Baseline Risk Assessment
Issue Based Risk Assessment
Pre Task Risk Assessment Templates
HIRA Competency & Appointment
Emergency Management
Site Establishment
End Of Job requirments
Monitoring and Auditing