Goslings
Demolition
Electrical disconnection
Plumbing disconnection
AC degas & disconnection
Plaster ceilings and key wall removal
Floor removal & grind
Kitchen, bathrooms, laundry demo
Fit off
Plaster cut outs
Plumbing fixtures
White goods
Accessories
Electrical
AC
Fit-out
Kitchen & vanity install
Stone template
Stone fit
Splashbacks
Doors & trim
Contract
QBCC
Site WH&S
Progress payment schedule
Client engagement letter
Selections confirmation & availability
Rough ins
Kitchen set out
Electrical pre-wire
Plumbing rough in
Drainage
AC ducting
Wet areas
Waterproofing
Bedding
Tiling
Shower screens & mirrors
Structural
Framing changes
Concrete cutting
Opening prep
Brickwork key in
Linings
Plaster & wet area
Cornice
Finishing
Cut-outs
Final electrical
Painting
Glazing
Window/door order
Floors
Skirting
Cleaning
Cabinetry design meeting